Sub topic 7
Defining Work Packages
This chapter assumes you know basic project management vocabulary (project, deliverable, stakeholder, milestone). It also assumes you can read an outline or tree structure and that you have a written scope statement. You should already know how a WBS is built level by level and how the 100% rule works.
What a work package is
A work package is the lowest-level element of a WBS. It is a deliverable, or a distinct piece of one, that you can estimate, assign to one responsible person or team, schedule and track. Every branch of the WBS ends in a work package. Everything above that level exists to group work packages and to roll up their figures.
Two points are easy to miss.
- A work package is named after what it produces ("Page templates"), not after the activity of producing it ("Design the templates").
- A work package is not a task list. Inside it, the team will later define activities, such as sketching, building and reviewing the templates. Activities belong to schedule planning, not to the WBS.
What makes a good work package
A work package is well defined when you can answer yes to each question in the table below.
| Test | Question to ask |
|---|---|
| Deliverable | Does it name a tangible result or a clearly bounded service? |
| Estimable | Can someone give an effort or cost figure without guessing wildly? |
| Assignable | Can one person or team be accountable for it? |
| Verifiable | Can you say when it is done, using acceptance criteria? |
| Bounded | Is it clear what is in it and what belongs in a neighbouring element? |
| Trackable | Can you report progress in short intervals? |
If one of these fails, the element is usually either too big (decompose it further) or too vague (rewrite the name and description).
Sizing: the rules of thumb
No single size is correct. Teams use guidelines, and you should pick one and apply it consistently.
- Effort limits. A common rule is that a work package takes between about 8 and 80 hours of effort.
- Reporting period. A work package should take no longer than one or two reporting periods. If you report weekly, a package lasting three months hides problems for too long.
- The 8/80 rule is one version of the first guideline. It is a heuristic, not a standard. A package of 100 hours is not wrong if it is cohesive and has one owner.
Sizes depend on risk and uncertainty. Familiar, low-risk work can sit in larger packages. Novel or high-risk work needs smaller ones, because small packages give earlier warning that something is off.
Worked example
Take the website relaunch used throughout this tutorial. Its design branch looks like this:
1 Website Relaunch
1.1 Design
1.1.1 Page templates
1.1.2 Style guide
1.2 Content
1.2.1 Migrated pages
1.2.2 New landing pagesConsider "1.1.1 Page templates". Check it against the tests.
- Deliverable: approved HTML/CSS templates for the home, article and contact pages.
- Estimable: the team has built similar templates before, and estimates 8 working days.
- Assignable: the design lead owns it.
- Verifiable: it renders correctly on the agreed browsers and the product owner approves it.
- Bounded: content writing is excluded, because it belongs to 1.2.
Now consider a weaker element, "1.2 Content". It is a parent, not a work package. It has several deliverables, probably several owners, and no single estimate that anyone could defend. It must be decomposed. "1.2.1 Migrated pages" is closer. It can be a work package if the number of pages is known. If the site has 40 pages in one template and 400 in twelve, you may need to split it by section so the estimate and progress reports mean something.
Work packages versus activities
New WBS authors often write verbs. The difference matters.
| Aspect | Work package | Activity |
|---|---|---|
| Expressed as | Noun (a result) | Verb (an action) |
| Lives in | The WBS | The schedule |
| Example | Style guide | Draft colour palette |
| Purpose | Defines scope | Defines how and when work is done |
A WBS full of verbs tends to drift toward a to-do list. It then misses deliverables that need no obvious "action", and it loses its role as a check on total scope.
Documenting the package
Once a work package is identified, record enough to make its boundary unambiguous. The WBS dictionary (covered in a later chapter) holds these records. A typical entry looks like this:
code: "1.1.1"
name: Page templates
description: Responsive HTML/CSS templates for the home, article and contact pages.
deliverable: Approved template files in the project repository
acceptance_criteria:
- Renders correctly on the agreed browsers and screen widths
- Approved by the product owner
responsible: Design lead
estimate_days: 8
assumptions:
- Style guide 1.1.2 is approved before build starts
excluded: Content writing (see 1.2)The excluded line is as useful as the description. Overlaps between packages cause double estimates and gaps cause missed work. Writing down what a package does not cover is the cheapest way to find both.
Estimates live at the leaves
Only work packages carry estimates. Parent elements get their figures by adding up their children, so they should never have an independent estimate. If a parent has its own number, that number may duplicate work already counted below it.
wbs = {
"code": "1", "name": "Website Relaunch",
"children": [
{"code": "1.1", "name": "Design", "children": [
{"code": "1.1.1", "name": "Page templates", "estimate_days": 8},
{"code": "1.1.2", "name": "Style guide", "estimate_days": 3},
]},
{"code": "1.2", "name": "Content", "children": [
{"code": "1.2.1", "name": "Migrated pages", "estimate_days": 10},
]},
],
}
def rollup(node):
children = node.get("children")
if not children:
return node["estimate_days"]
for child in children:
if not child["code"].startswith(node["code"] + "."):
raise ValueError(f"{child['code']} is not under {node['code']}")
return sum(rollup(child) for child in children)
print(rollup(wbs)) # 21A leaf without estimate_days raises a KeyError. That is useful: an unestimated work package is a defect in the plan, and the error shows it immediately.
Common errors
- Packages that are too large. A 300-hour package cannot be tracked. Progress stays at "in progress" until it suddenly finishes or fails.
- Packages that are too small. Tracking a 2-hour package costs more than the work. It also produces a WBS with hundreds of lines nobody reads.
- Several owners. If two teams share a package, split it or name one accountable owner who coordinates the other. Shared accountability usually means nobody is accountable.
- Overlap. Two packages both claim "Test the templates". One estimate is wasted, or both teams assume the other did it.
- Verb names. "Do testing" is an activity. "Test report" is a deliverable.
- Management work missing. Planning, reporting and coordination consume real effort. Give them a package, as in "1.4.1 Project plan and status reports".
- No acceptance criteria. Without them, "done" is an opinion and disputes follow.
How packages are used downstream
Work packages are the link between scope and the other plans.
- Schedule: each package is broken into activities that are sequenced and given durations.
- Cost: package estimates are summed into budgets.
- Responsibility: each package has one owner, which feeds responsibility assignment.
- Progress: reporting is done against packages, so their size sets how fine your visibility is.
A short check procedure
When you reach what you think is a leaf, run this sequence.
- Name it as a noun phrase describing the result.
- Write one sentence of description and one of exclusion.
- List acceptance criteria.
- Name one owner.
- Produce an estimate. If you cannot, decompose or investigate first.
- Compare its size with your team's guideline, and split or merge as needed.
Exercise
A WBS contains the leaf element "Build and test the login feature", estimated at 160 hours, owned jointly by the front-end and back-end teams. Name three problems with it as a work package and suggest a better split.
Show answer
First, the name describes activities ("build and test"), not a deliverable. Second, 160 hours is large for tracking, so progress will be opaque. Third, joint ownership leaves nobody accountable. A better split is by deliverable and owner, for example "Login screen" (front-end team), "Authentication service" (back-end team) and "Login test report" (a named test owner). Each gets its own description, acceptance criteria, exclusions and estimate, and the parent "Login feature" rolls them up.
Exercise
In the Python roll-up above, why must only leaf elements carry estimates? What goes wrong if "1.1 Design" is given its own 15-day estimate while its children total 11?
Show answer
A parent's figure is meant to be the sum of its children. A separate parent estimate produces two competing totals, 15 and 11, and no way to tell whether the extra 4 days is real work missing from the WBS (a 100% rule violation) or padding. The roll-up would also ignore it or double count it, depending on how it is written. Keep estimates at the leaves and add any contingency explicitly, as its own labelled element or reserve.