Start from the project scope
A work breakdown structure (WBS) is only as good as the scope it divides. This chapter covers how to read a project scope statement, pull out the deliverables that become the top-level WBS elements, and spot scope gaps before you start decomposing. Later chapters cover decomposition, numbering, and estimating.
Prerequisites
This chapter assumes you already know:
- Basic project management vocabulary: project, deliverable, stakeholder, milestone.
- What a project scope statement is. You need a written one, or an equivalent description of what the project must deliver.
- How outlines and tree structures work (a parent with indented children).
You do not need any scheduling or estimating experience. The examples use a website relaunch project. The chapter follows it from scope statement to first-level WBS elements.
What the WBS divides
A WBS divides the project's total scope into a hierarchy of deliverables and work packages. It does not invent scope. It shows scope that has already been agreed, in a form you can estimate, assign, and track.
That has two consequences:
- If something is not in the scope, it does not belong in the WBS.
- If something is in the scope but missing from the WBS, nobody will plan, estimate, or do it.
The WBS is therefore a checkable copy of the scope. Weak scope produces a weak WBS, however carefully you decompose.
Project scope versus product scope
Two terms are easy to confuse:
| Term | Meaning | Website relaunch example |
|---|---|---|
| Product scope | The features and characteristics of what you deliver | A responsive site with home, article, and contact pages |
| Project scope | All the work needed to deliver that product | Design, content migration, hosting setup, testing, project management |
The WBS covers project scope. It includes the product and also the work that supports it, such as project management and documentation. A WBS that lists only product features will leave out work that still costs time and money.
What a scope statement contains
A scope statement usually has these parts. Each one feeds the WBS in a different way.
| Scope statement part | What it tells you | How you use it for the WBS |
|---|---|---|
| Project objectives | Why the project exists | Check that every element supports an objective |
| Deliverables | What must be produced | Source of the top-level elements |
| Acceptance criteria | How deliverables are judged complete | Later copied into WBS dictionary entries |
| Exclusions | What is deliberately out of scope | Stops scope creep and gets recorded as "excluded" |
| Assumptions and constraints | What you rely on and what limits you | Shape sequencing and risk, and are noted on elements |
Read the exclusions as carefully as the deliverables. A clearly stated exclusion gives you a ready answer when someone asks, "Isn't that part of the project?"
A sample scope statement
Here is a short statement for the running example.
Project: Website Relaunch
Objective:
Replace the current company website with a new site that works on
phones and is easy for staff to update.
In scope:
- Page templates and a style guide
- Migration of the 40 existing pages
- Three new landing pages
- A hosting environment and content management configuration
- Project plan and monthly status reports
Out of scope:
- Writing new articles
- Search engine advertising campaigns
Acceptance:
- Site renders correctly on the agreed browsers and screen widths
- Product owner approves templates and landing pages
Assumptions:
- The style guide is approved before template build startsThis is short on purpose. Real statements run longer, but the same parts appear.
Deriving top-level elements
Follow these steps to get from a scope statement to level 2 of the WBS. Level 1 is the project itself.
- Mark every deliverable in the "in scope" list. Treat each noun phrase that names something produced as a candidate.
- Name each candidate as a thing, such as "Style guide" or "Migrated pages". Do not use a verb phrase like "Write the style guide".
- Group related deliverables under a shared parent. In the example, templates and the style guide both belong to design.
- Add the project management deliverables, which scope statements often leave implicit.
- Check the exclusions. Nothing on that list may appear in the result.
Applied to the example, the groups are:
- Design: page templates, style guide.
- Content: migrated pages, new landing pages.
- Platform: hosting environment, content management configuration.
- Project management: project plan and status reports.
Grouping gives the outline below. The chapter on organizing the first levels explains when to group by deliverable and when by phase.
1 Website Relaunch
1.1 Design
1.2 Content
1.3 Platform
1.4 Project managementChecking the result against the scope
Before you decompose further, compare the draft against the scope in both directions.
- Scope to WBS: take each in-scope item and find where it appears. An item with no home is a gap.
- WBS to scope: take each WBS element and find the scope text that justifies it. An element with no source is either hidden extra work or a sign the scope statement is incomplete.
You can run the first check mechanically if you keep your scope items in a list. The script below flags scope items that no WBS element mentions.
scope_items = [
"Page templates",
"Style guide",
"Migrated pages",
"New landing pages",
"Hosting environment",
"Content management configuration",
"Project plan and status reports",
]
wbs_names = [
"Website Relaunch",
"Design",
"Content",
"Platform",
"Project management",
"Page templates",
"Style guide",
"Migrated pages",
]
missing = [item for item in scope_items if item not in wbs_names]
print("Scope items with no WBS element:")
for item in missing:
print(" -", item)Run against this draft, it prints four items: new landing pages, hosting environment, content management configuration, and the project plan. That is expected, because the draft stops at level 2 and only some level 3 elements exist. The check is useful once the WBS is fully decomposed, and it shows the idea: every scope item needs a home.
Common problems with the scope
Watch for these when reading a scope statement.
- Vague deliverables. "Improve the website" names no deliverable. Ask what will exist at the end that did not exist before.
- Activities listed as scope. "Testing" is an activity. The deliverable is something like "Test report" or "Tested site". Ask which.
- Missing project management work. Planning, reporting, and coordination take effort even when nobody lists them.
- Missing exclusions. If nobody wrote down what is out, assume stakeholders have different ideas about it. Raise this before decomposing.
- Conflicting acceptance criteria. If two stakeholders define "done" differently, the deliverable cannot be bounded.
What to carry forward
- The WBS is a structured copy of agreed scope, so start from the scope statement.
- Use project scope, not only product scope. Include project management.
- Extract deliverables as nouns and group them into the first few elements.
- Check the draft against the scope in both directions, and keep exclusions out.
The next chapter looks at deliverable-oriented thinking in more detail, and explains why elements named as things serve you better than elements named as actions.
Exercise
A scope statement for an office move lists these in-scope items: "Packing the old office", "Network cabling in the new office", "Furniture installation", and "Weekly status reports". It lists "Disposal of old furniture" as out of scope. Rewrite the first three in-scope items as deliverables, name the missing group that the status reports belong to, and say whether "Disposal of old furniture" belongs in the WBS.
Show answer
Deliverables as nouns: "Packed contents of old office" (or "Packed boxes"), "Cabled network in new office", and "Installed furniture". The status reports belong under a project management element, for example "Project management", with "Status reports" beneath it. "Disposal of old furniture" does not belong in the WBS because it is out of scope. Record it as an exclusion instead.
Exercise
You compare a draft WBS against its scope statement and find an element, "Search engine optimization audit", that no sentence in the scope mentions. List two possible explanations and what you should do about each.
Show answer
Either the element is extra work added without approval, so remove it or take it through change control, or the scope statement is incomplete and the work is genuinely wanted, so ask the sponsor to confirm and update the scope statement before keeping the element. In both cases the WBS and the scope must agree afterward.