Sub topic 11
Documenting elements in a WBS dictionary
What the WBS dictionary is and why it exists
This chapter assumes you can already build a hierarchy of deliverables, number its elements, and identify work packages. If you cannot yet, review the chapters on decomposition, work packages and numbering first.
A WBS shows the shape of the scope, but its element names are short. "Page templates" could mean three templates or thirty. The reader cannot tell what counts as done, who owns the work, or what is left out. The WBS dictionary fills that gap. It is a companion document that holds one entry for each WBS element, keyed by the element's code.
The dictionary does three jobs:
- It fixes the meaning of each element. Two people reading "Migrated pages" should picture the same work.
- It prevents overlap. An explicit exclusion line makes the mutual exclusivity of sibling elements checkable.
- It carries the data other plans need. Owners, estimates, and acceptance criteria are inputs to estimating, scheduling, and quality control.
The numbering you assigned earlier is what makes this possible. The code is the primary key. Every entry must match exactly one WBS element, and every work package must have an entry.
What goes in an entry
Entries vary by organization, but a useful entry has these fields.
| Field | Purpose | Example |
|---|---|---|
| Code | Links the entry to the WBS element | 1.1.1 |
| Name | Matches the WBS element name exactly | Page templates |
| Description | States the scope of the element in plain words | Responsive HTML/CSS templates for the home, article and contact pages |
| Deliverable | Names the tangible output | Approved template files in the project repository |
| Acceptance criteria | Testable conditions for "done" | Renders correctly on agreed browsers; approved by the product owner |
| Responsible | One accountable person or role | Design lead |
| Estimate | Effort or cost, normally at work package level | 8 days |
| Assumptions | Conditions the estimate depends on | Style guide 1.1.2 is approved before build starts |
| Exclusions | Nearby work that belongs elsewhere | Content writing (see 1.2) |
Some teams add more fields, such as required resources, milestones, quality requirements, and contract information. Add a field only if someone uses it. An empty column that nobody reads creates maintenance work and nothing else.
A complete entry
The following entry is for work package 1.1.1 from the website relaunch example. It is written in YAML so that it can be stored in version control and checked by a script.
code: "1.1.1"
name: Page templates
description: Responsive HTML/CSS templates for the home, article and contact pages.
deliverable: Approved template files in the project repository
acceptance_criteria:
- Renders correctly on the agreed browsers and screen widths
- Approved by the product owner
responsible: Design lead
estimate_days: 8
assumptions:
- Style guide 1.1.2 is approved before build starts
excluded: Content writing (see 1.2)Look at how each field does its work:
- The description names the three pages. A reviewer can count them, so scope growth is visible.
- Both acceptance criteria can be tested. "Looks good" would not be.
- The assumption records a dependency on 1.1.2. If the style guide slips, the estimate is no longer valid, and the entry says why.
- The exclusion points to 1.2. This is the line that stops design and content from claiming the same work.
Writing good entries
Describe scope, not method
The description says what is delivered, not how the team will do it. "Build templates using the agreed framework" mixes in a method. "Responsive templates for three named pages" states scope. Method belongs in the schedule and the work instructions.
Make acceptance criteria testable
A criterion is testable if two people would reach the same pass or fail verdict. Replace vague words with measures or named approvals.
| Vague | Testable |
|---|---|
| Fast page loads | Home page loads in under 3 seconds on the agreed test connection |
| Stakeholders are happy | Product owner signs off in writing |
| Works on mobile | Renders without horizontal scrolling at 360 px width and above |
Assign one responsible party
Several people may do the work, but one person or role answers for the element. Shared ownership usually means no ownership when a problem appears.
Record exclusions where boundaries are close
You do not need an exclusion for every element. Write one where a reader could plausibly assign the work to either of two siblings. Content versus design, hosting versus configuration, and testing versus building are typical cases.
Which elements get entries
Work packages need full entries. Higher-level elements need less. A parent's description can be a single sentence stating that it comprises its children, and its estimate is the sum of theirs. Do not type a parent's estimate by hand. A typed value can drift out of agreement with the children, and then the dictionary contradicts itself.
Checking the dictionary automatically
A dictionary kept as structured data can be checked by a script. The sketch below verifies that every leaf of a WBS has an entry, that no entry points to a missing element, and that every work package has the required fields. It runs as shown.
wbs_leaves = {"1.1.1", "1.1.2", "1.2.1"}
entries = {
"1.1.1": {"name": "Page templates", "responsible": "Design lead",
"acceptance_criteria": ["Approved by the product owner"],
"estimate_days": 8},
"1.1.2": {"name": "Style guide", "responsible": "Design lead",
"acceptance_criteria": [], "estimate_days": 3},
"1.3.9": {"name": "Orphan entry", "responsible": "Nobody",
"acceptance_criteria": ["Exists"], "estimate_days": 1},
}
required = ["name", "responsible", "acceptance_criteria", "estimate_days"]
problems = []
for code in sorted(wbs_leaves - entries.keys()):
problems.append(f"{code}: work package has no dictionary entry")
for code in sorted(entries.keys() - wbs_leaves):
problems.append(f"{code}: entry does not match any work package")
for code, entry in sorted(entries.items()):
for field in required:
if not entry.get(field):
problems.append(f"{code}: missing {field}")
for problem in problems:
print(problem)It prints three problems: 1.2.1 has no entry, 1.3.9 matches no work package, and 1.1.2 has no acceptance criteria. Running a check like this before each review catches gaps earlier than a meeting does.
Common errors
- Copying the element name into the description. "Style guide: the style guide" adds nothing. State what the guide contains.
- Activity language. "Design and test pages" describes work steps. Name the deliverable instead.
- Estimates without assumptions. An estimate of 8 days means little without the conditions behind it.
- No update path. A dictionary written once and never revised becomes false. Change it through the same change control process as the WBS, and keep the version and date in the file.
- Overlapping descriptions. If two entries could both claim a task, add an exclusion to each and fix the WBS if the overlap is real.
Exercises
Exercise
A WBS dictionary entry for work package 1.2.1 "Migrated pages" says: "Move the old pages to the new site." It has no acceptance criteria, no exclusions, and an estimate of 10 days. List three specific improvements.
Show answer
(1) Describe the scope measurably, for example "All 120 pages listed in the content inventory, migrated to the new content management system." (2) Add testable acceptance criteria, such as "Links resolve with no 404 errors, and the content owner signs off." (3) Add an exclusion that separates this work from nearby work, for example "New landing pages (see 1.2.2); rewriting of page text." An assumption stating the page count behind the 10-day estimate is also worthwhile.
Exercise
The parent element 1.1 "Design" has a hand-typed estimate of 12 days in the dictionary. Its children 1.1.1 and 1.1.2 are estimated at 8 and 3 days. What is wrong, and how do you fix it?
Show answer
The children sum to 11 days, so the typed 12 disagrees with them. Either the child estimates or the parent figure is wrong, and nobody can tell which. Remove the typed estimate and compute the parent as the sum of its children (11). If 12 reflects real extra work, find it and add it as a work package or correct a child estimate.