Sub topic 12
Reading the Map: Bottlenecks, Excess Inventory, and Improvement Opportunities
Assume you know how to read process boxes, data boxes, inventory triangles, material-flow arrows, and information-flow arrows. You should also be comfortable with takt time, lead time, process time, and basic rates.
A current-state map is useful when it helps you explain where work waits, where flow is restricted, and why delivery takes as long as it does. Read the map from the customer backward through the process. Look for evidence before proposing a solution.
Find the bottleneck
A bottleneck is a step that limits the output of the whole value stream. A step can be a bottleneck because its cycle time is longer than takt time, because it has limited capacity, or because it frequently stops.
For example, suppose customer demand creates a takt time of 60 seconds per unit:
| Process step | Cycle time | Queue before step | Initial signal |
|---|---|---|---|
| Stamping | 1 s | 4,500 units | Large queue |
| Welding | 39 s | 1,350 units | Moderate queue |
| Assembly | 46 s | 900 units | Near takt |
| Shipping | 62 s | 450 units | Slower than takt |
Shipping is slower than takt, so it cannot consistently meet demand at the current staffing and equipment level. Stamping has the largest queue, but that does not automatically make it the bottleneck. The queue may have accumulated because an upstream process produced too much or because shipping was unavailable.
Check three signals together:
- A process cycle time greater than takt.
- Inventory growing before the process.
- The process having high utilization, downtime, or changeover losses.
A bottleneck can move after an improvement. Recheck the complete map instead of assuming that the original constraint remains the constraint.
Read inventory as waiting time
Inventory on the map represents work that has not reached the next step. Convert each inventory quantity into approximate waiting time:
waiting days = queue units / customer demand per day
If 1,350 units wait before welding and demand is 450 units per day, that queue represents three working days of waiting. The quantity becomes easier to compare with process time when expressed as time.
Excess inventory often indicates one or more of these conditions:
- Processes are scheduled independently.
- Upstream work is pushed without a downstream signal.
- Batch sizes are too large.
- Demand or capacity is unstable.
- Quality problems create rework or hidden queues.
Inventory is not always waste. Some stock may protect a process from known variation or support a required shipment policy. Mark the reason for the inventory. If no clear reason exists, treat it as an improvement opportunity.
Mark opportunities without jumping to solutions
Use the map to record a condition, its evidence, and a question for investigation. For example:
- Condition: shipping exceeds takt.
- Evidence: 62-second cycle time versus 60-second takt.
- Investigation question: Is the loss caused by handling, paperwork, downtime, or insufficient capacity?
Useful improvement marks include excess inventory, long changeovers, repeated scheduling, rework loops, uneven cycle times, and missing pull signals. Rank opportunities by their effect on customer delivery and total lead time, not by how easy they look.
A short process time beside many days of waiting suggests a flow problem. A single slow step suggests a capacity problem. Several queues and frequent schedule changes suggest a system problem. The map cannot prove the cause by itself, so validate important findings at the point of work.
Use a simple diagnostic
takt_s = 60
steps = [
("Stamping", 1, 4500),
("Welding", 39, 1350),
("Assembly", 46, 900),
("Shipping", 62, 450),
]
daily_demand = 450
for name, cycle_s, queue_units in steps:
wait_days = queue_units / daily_demand
signals = []
if cycle_s > takt_s:
signals.append("over takt")
if wait_days >= 3:
signals.append("large queue")
print(name, f"{wait_days:.1f} waiting days", ", ".join(signals) or "no flagged signal")Use the output to focus observation. It is a screening tool, not proof of root cause.
Exercise
A process has a 55-second cycle time and a queue of 1,800 units. Customer demand is 450 units per day, and takt time is 60 seconds. What should you investigate first?
Show answer
Investigate the three-day queue. The process is under takt, so the queue may result from upstream overproduction, batch sizing, uneven arrivals, or a downstream restriction.