Sub topic 4
Mapping Symbols and How the Map Is Laid Out
Assume you know the basic stages of a production, service, or software delivery process, and can distinguish customer demand from internal activity. This chapter focuses on the visual grammar of a current-state value stream map: what the main symbols mean, where to place them, and how to keep the map readable.
The basic layout
A value stream map usually reads from left to right. The supplier appears at the upper left, the customer at the upper right, and the process steps run horizontally between them. Material or work flows along the middle. Information flows above the process. A timeline runs along the bottom.
This arrangement separates three questions:
- What work happens, and in what order?
- Where does work wait between steps?
- How do customer requirements and production instructions move?
Use the same layout even when the process is a service or software workflow. Replace physical material with work items, cases, requests, or releases.
Common symbols
| Symbol or visual element | Meaning | Typical location |
|---|---|---|
| Process box | A process step treated as one unit of analysis | Middle flow |
| Data box | Facts about a process, such as cycle time or uptime | Under a process box |
| Inventory triangle | Work waiting between process steps | Between process boxes |
| Truck or shipment arrow | External movement to or from a supplier or customer | Map edges |
| Solid arrow | Material or work movement | Middle flow |
| Dashed arrow | Information movement | Upper flow |
| Lightning bolt | An improvement opportunity or problem to investigate | Beside the relevant area |
| Supermarket | Controlled inventory that replenishes downstream use | Between linked processes |
| Timeline | Waiting time and processing time | Bottom of map |
A process box should represent a meaningful control point, not every individual motion. For example, “Assemble unit” may be useful, while “Pick up screw” is usually too detailed for a family-level map.
A data box records measurements that explain performance. Common entries include cycle time, changeover time, uptime, number of operators, batch size, and available working time. Record the unit for every number. “Cycle time: 46” is incomplete; “cycle time: 46 seconds per unit” is usable.
An inventory triangle marks a queue. Write the quantity beside it, and identify whether the quantity is raw material, work in process, or finished goods. In a service map, label the queue with the number of open cases or requests.
Material and information flow
A solid arrow shows the direction of work. It does not prove that the flow is continuous. An inventory triangle between two process boxes often means the upstream step produces before the downstream step is ready. This is push flow.
A pull relationship means the downstream process signals the upstream process to replenish what it used. A supermarket symbol can show the controlled buffer that supports this relationship. Do not label every connection “pull” merely because work eventually moves downstream. Confirm how replenishment actually occurs.
Information arrows normally appear above the process flow. They can connect the customer to an order-entry system, a planning function to production, or one process to another. Label the information with its form and frequency, such as “daily schedule,” “electronic order,” or “weekly forecast.”
Layout rules that preserve meaning
Keep the main flow at one level whenever possible. If a process branches, show the branch clearly and state why it exists. Avoid crossing arrows. Crossed lines force readers to guess which connection is intended.
Place measurements next to the process or queue they describe. Use a legend if the team uses symbols that are not standard or obvious. Include a date and the product family covered by the map so that readers know the map is a current snapshot rather than a permanent process specification.
Exercise
Where should you place a dashed arrow labeled “daily production schedule” if a planning function sends it to the first process?
Show answer
Place it above the material flow, connecting the planning function to the first process box. The dashed line identifies information flow, while the label identifies its content and frequency.