Sub topic 7
Customer Demand and Takt Time
Assume you can read a basic value stream map, identify process steps, and calculate simple rates. This chapter focuses on setting the demand pace for a current-state map. Later chapters use that pace to compare process capacity with customer need.
Start with the customer demand rate
Customer demand is the quantity the customer expects over a defined period. Use a consistent unit, such as units per day, orders per week, or claims per month. For a current-state map, use actual shipments or firm demand when available. Do not substitute a machine's maximum output for customer demand.
Convert the demand period to the same period used for available work time.
For example:
- Customer demand: 450 units per day
- Available production time: 7.5 hours per day
- Available time in seconds: 7.5 × 60 × 60 = 27,000 seconds
Calculate takt time
Takt time is the available working time divided by customer demand. It describes the required average pace to make one unit and keep up with demand.
AVAILABLE_SECONDS_PER_DAY = 27000
DAILY_DEMAND = 450
takt_s = AVAILABLE_SECONDS_PER_DAY / DAILY_DEMAND
print(f"Takt time: {takt_s:.0f} seconds per unit")The result is 60 seconds per unit. On average, one completed unit must leave the process every 60 seconds during available production time.
| Input or result | Value |
|---|---|
| Available time | 27,000 seconds/day |
| Customer demand | 450 units/day |
| Takt time | 60 seconds/unit |
Takt is a demand signal, not a prediction of how fast one machine can run. It also is not the same as cycle time. Cycle time is the time a process takes to complete one unit. Compare the two:
- Cycle time below takt: one process position may have enough capacity, depending on downtime, staffing, changeovers, and quality losses.
- Cycle time equal to takt: the process has little protection against variation.
- Cycle time above takt: one position cannot meet demand without reducing the cycle time, adding parallel capacity, changing staffing, or altering the work.
A 62-second shipping step is slower than a 60-second takt. That does not automatically mean the entire system ships only one unit every 62 seconds. Multiple people or parallel positions may increase capacity. Record that capacity explicitly rather than hiding it in an average.
Show takt on the current-state map
Place the takt calculation near the customer or data area of the map. Then compare each process cycle time with takt. This comparison helps reveal where the current state cannot reliably match demand.
Common errors
- Using scheduled hours instead of net available time.
- Mixing units, such as seconds per unit with units per hour.
- Using average monthly demand when daily demand varies sharply without noting the assumption.
- Treating takt as a target for workers to exceed continuously. Takt sets the required average pace; safety, quality, and stable work still matter.
- Comparing takt with a process cycle time while ignoring parallel stations. Compare takt with effective capacity for the whole process.
Exercise
A line has 21,600 net available seconds per day and demand of 360 units per day. One process has a 65-second cycle time. What is takt time, and what issue should the map flag?
Show answer
Takt time is 21,600 ÷ 360 = 60 seconds per unit. The 65-second process is slower than takt, so the map should flag a capacity gap for investigation. Check parallel stations, downtime, staffing, and improvement options before deciding on a countermeasure.