Sub topic 13
Common Pitfalls When Mapping the Current State
Assume you already understand process boxes, data boxes, inventory symbols, takt time, and basic lean waste categories. This chapter focuses on errors that make a current-state value stream map look precise while describing the wrong system.
Treating assumptions as facts
A map should describe what happens now, not what procedures say should happen. Do not copy standard cycle times, planned staffing, or target inventory levels without checking them at the point of work.
Record:
- When and where you observed the process.
- Whether the data came from observation, a system report, or an interview.
- The product, shift, batch, and conditions included.
- Any unusual event, such as a breakdown or rush order.
A single observation may be useful, but it is not automatically representative. Observe enough cycles to see normal variation. Use a range or a clearly labeled average when variation affects the conclusion.
Mixing unlike work
A product family contains items that pass through similar process steps. A common mistake is mapping several unrelated products together because they share the same customer or department.
This can produce false cycle times, incorrect inventory totals, and a misleading bottleneck. If products follow different routes, map them separately or document the route differences clearly.
Also keep the map boundary consistent. For example, do not include supplier inventory for one material while excluding it for another. State whether the map starts at the supplier, receiving area, order entry, or another defined point.
Using averages that hide the problem
Averages can hide changeovers, rework, waiting, and short stoppages. A process with a 40-second average cycle time may sometimes run at 25 seconds and sometimes at 90 seconds. The average alone does not explain whether demand can be met.
Capture the measures that affect flow:
- Cycle time and its variation.
- Changeover time and batch size.
- Uptime or downtime.
- First-pass yield and rework.
- Number of operators.
- Queue size by location.
- Frequency of expedited work.
Separate processing time from waiting time. A part may spend 30 seconds being worked on and two days waiting for the next operation.
Counting inventory incorrectly
Inventory is usually shown between process steps, but teams often count only visible finished units. Include raw material, work in process, finished goods, carts, pallets, cases, and digital queues when they represent waiting work.
Use one unit of measure consistently. If a pallet contains 100 units, record both the number of pallets and the unit count when either could affect the calculation. Record inventory at a specific time because the quantity changes throughout the day.
The following relationship helps expose inconsistent counts:
Confusing push with pull
Material moving to the next step does not prove that the next step requested it. In a push system, an upstream process produces from a schedule, forecast, or local target. In a pull system, downstream consumption triggers replenishment within defined limits.
Show the actual signal. It may be a kanban card, a replenishment scan, a dispatch list, or a verbal instruction. If no signal exists, label the connection as push rather than drawing a pull loop because it appears desirable.
Omitting information flow
Maps often show material clearly but reduce information flow to one arrow labeled “schedule.” This hides how priorities change and why queues form.
Record who creates the schedule, how often it changes, and how each process receives it. Include customer orders, forecasts, production control, dispatch lists, and rework instructions when they affect the path.
Editing the map into a solution
Do not remove delays, combine departments, or add future-state controls while drawing the current state. Use notes, icons, or a separate improvement list to mark opportunities. Preserve the observed condition so another person can verify it.
Exercise
Exercise
A team reports a 45-second average cycle time, but observed cycles range from 20 to 85 seconds. What should the map record?
Show answer
Record the average with the observation period and variation, then investigate the causes of the range. Do not use the average alone to decide whether the process meets takt time.