Sub topic 8
Material Flow, Inventory, and Push Versus Pull
Assume you understand basic process steps, value stream maps, and simple rates such as units per day. This chapter focuses on how material moves between process steps, how inventory reveals waiting, and how to distinguish push flow from pull flow.
Material flow on the current-state map
Material flow shows the physical path from incoming materials to the customer. Draw the process steps in the order that work happens. Add inventory triangles between steps when units wait, are stored, or are not yet being processed.
Inventory includes more than finished goods in a warehouse. It can include:
- Raw material waiting for the first operation
- Work in process between operations
- Parts waiting for inspection, transport, or approval
- Finished goods waiting for shipment
Record the quantity at each location during the mapping period. Also record whether the quantity changes sharply by shift, day, or product type. A single count can hide a recurring pattern.
The map should show the actual path, including rework loops, temporary storage, and long transfers. If parts regularly leave the main path and return later, draw that movement or note it beside the map.
Inventory as a measure of waiting
Inventory often indicates that work is not flowing continuously. A queue forms when an upstream process produces faster than the next process can consume, or when the next process is unavailable.
Convert inventory into waiting time with this relationship:
Waiting time in working days = inventory units ÷ average daily demand
For example, 1,200 units waiting before welding, with demand of 450 units per day, represent about 2.67 working days of potential waiting. This calculation estimates average delay. It does not prove that every unit waits exactly that long.
| Map observation | Possible meaning | Question to investigate |
|---|---|---|
| Large queue before one step | The step may be slower or less reliable | Is this step the constraint, or is production released too early? |
| Small queue before a frequently stopped step | The upstream process may be starved | Why is material not replenished in time? |
| Finished goods above normal demand | Production may be based on forecasts | What customer signal authorizes production? |
Inventory can protect a process from shortages, but it also hides problems. Excess stock can conceal downtime, quality defects, uneven work, and unreliable schedules. Mark unusually large queues as improvement opportunities rather than treating them as permanent requirements.
> callout warning > Do not assume that every inventory buffer is waste. Some stock protects against supplier lead time, shared equipment, transportation delays, or demand variation. Record the reason for each buffer before proposing its removal.
Push and pull flow
Push production releases work because a schedule, forecast, or target says to produce. Each process may make its own decision without checking whether the next process needs the output. This often creates growing queues and uneven priorities.
Pull production authorizes replenishment when the downstream process consumes material. A signal can be a kanban card, an empty container, a barcode scan, or a digital order. The signal defines what quantity and type should be replaced.
| Push characteristic | Pull characteristic |
|---|---|
| Work starts from a plan or forecast | Work starts from downstream consumption |
| Each step may produce to its local target | Replenishment follows an agreed signal |
| Queues grow when production exceeds demand | A limit controls the amount in the loop |
| Priority changes can create expediting | Standard signals make priorities visible |
A process can contain both systems. For example, a supplier may push large batches into a plant, while assembly pulls parts from a supermarket, which is a controlled inventory location. Label each connection on the current-state map. Do not call a flow pull merely because two steps are physically close.
Reading the map for improvement
Look for material that moves backward, waits without a clear signal, or is produced in batches larger than customer demand requires. Compare the quantity in each queue with the consumption rate. Then ask:
- What event releases work into this queue?
- Who owns the inventory?
- What quantity is allowed?
- What happens when the limit is reached?
- What happens when the downstream process needs material?
A future-state design may reduce batch sizes, establish supermarkets, connect processes with a first-in-first-out lane, or create a pacemaker process. The current-state map should record the evidence first. Design choices belong after the team understands the present flow.
Exercise
A queue contains 900 units, and the customer demand is 450 units per working day. What waiting time does the queue represent, and what further question should you ask before removing it?
Show answer
It represents about 2 working days of demand. Ask why the buffer exists, such as protection from downtime, supplier delay, or demand variation, before removing it.