Sub topic 14
From Current State to Future State
This chapter assumes you can read a current-state value stream map, calculate takt time and lead time, and distinguish process time from waiting time. The goal is not to redraw the current state neatly. The goal is to turn verified observations into a useful starting point for future-state design.
Treat the current state as a baseline
A current-state map describes how work flows today, including delays, queues, rework, batching, and scheduling rules. It is a baseline for comparison. It is not a target process and should not be cleaned up to make the operation look better.
Before handing it off, check that the map has:
- A clearly named product family or service type.
- Defined start and end points.
- Customer demand and available working time.
- Process cycle times and relevant uptime or quality data.
- Inventory or work-in-process quantities at each queue.
- Material or work flow arrows.
- Information flow and scheduling points.
- Calculated wait time, process time, and total lead time.
- The date, people involved, and assumptions used.
Record uncertainty instead of hiding it. For example, write “queue count observed at 10:00” or “average demand over the previous 20 working days.” Future-state decisions are only as reliable as the evidence behind them.
Convert observations into design questions
The handoff should identify conditions that the future state must address. Do not jump directly from a problem label such as “too much inventory” to a solution such as “add kanban.” First describe the operating condition and its effect.
| Current-state observation | Future-state design question |
|---|---|
| Assembly receives large batches from welding | Where can flow be established, and what batch size is necessary? |
| Shipping is slower than takt time | Can the work be balanced, split, simplified, or scheduled differently? |
| Production is released by a central schedule at every step | Where can a pacemaker process control replenishment? |
| Orders wait several days between processes | What limits, signals, or layout changes will reduce the queue? |
A pacemaker process is the point in the value stream where production is scheduled. Downstream processes often follow customer demand, while upstream processes replenish what the pacemaker consumes.
Make the handoff explicit
Mark improvement opportunities directly on the map. Useful categories include:
- Flow: connect sequential steps where practical.
- Pull: replace forecasts or uncontrolled releases with replenishment signals.
- Balance: compare each process with takt and redistribute work.
- Quality: prevent defects from moving downstream.
- Availability: reduce downtime that interrupts the required rate.
- Information: simplify schedules and make priorities visible.
- Inventory: set a deliberate quantity and a reason for each buffer.
Separate facts from proposals. A fact might be “900 units wait before assembly.” A proposal might be “create a supermarket of 300 units.” The future-state team must be able to tell which statements came from observation and which require testing.
Define measurable future-state targets
Use the current map to establish a small set of target measures. Examples include lead time, process cycle efficiency, total work-in-process, first-pass yield, changeover time, and adherence to takt. Each target needs a boundary and a measurement method.
Do not promise that every step will run continuously. Some processes may require batches because of changeovers, shared equipment, safety constraints, or supplier rules. Document these constraints so the design does not assume impossible flow.
A useful handoff includes:
- The validated current-state map.
- The demand and operating-time assumptions.
- The major constraint and waste observations.
- The proposed scope for the future-state workshop.
- Open questions requiring data or experiments.
- The owner and date for each follow-up action.
Review the transition path
Future-state design should lead to an implementation plan, not remain a drawing. Sequence changes so that the team can learn safely. For example, measure demand and cycle times first, establish a small controlled buffer, test a replenishment signal, and then adjust staffing or layout.
Exercise
The map shows 7200 units of work in process and shipments of 450 units per day. What average lead time should the future-state team use as a cross-check?
Show answer
Use Little's Law: lead time = work in process / throughput = 7200 / 450 = 16 working days. Investigate any large difference between this value and the map's timeline.