Sub topic 10
Building the Timeline: Wait Time, Process Time, and Lead Time
What the timeline measures
Assume you already know how to read a current-state map, collect inventory counts, and calculate demand and takt time. This chapter uses those map elements to build the timeline below the material-flow symbols.
The timeline separates two kinds of time:
- Wait time is the time a unit spends between process steps, usually represented by inventory.
- Process time is the time workers or machines actively transform or handle the unit.
Lead time is the total time from the start of the mapped stream to delivery:
\[ \text{Lead time} = \text{Wait time} + \text{Process time} \]
A timeline makes the central lean question visible: how much of the customer's total wait is actual work?
Convert inventory into wait time
For a stable process, estimate the wait represented by an inventory triangle with:
\[ \text{Wait time in days} = \frac{\text{Inventory units}}{\text{Daily demand}} \]
For example, if 4,500 units wait before stamping and the customer requires 450 units per day:
\[ 4{,}500 / 450 = 10 \text{ working days} \]
Use the demand rate that matches the map's product family. Do not divide by machine capacity. The timeline represents how long the current stream takes to serve customers, not how fast one operation could theoretically run.
Build the current-state timeline
Place wait times on the upper portion of the timeline and process times on the lower portion. Sum each category separately, then combine them.
| Timeline component | Calculation | Result |
|---|---|---|
| Total wait time | 10 + 3 + 2 + 1 working days | 16 working days |
| Total process time | 1 + 39 + 46 + 62 seconds | 148 seconds |
| Lead time | 16 working days + process time | About 16.01 working days |
The process time is usually converted to days before adding it to wait time. With 27,000 available working seconds per day:
\[ 148 / 27{,}000 = 0.00548 \text{ working days} \]
Therefore, the lead time is approximately 16.0055 working days. The small process-time fraction is important conceptually, even when it barely changes the total. It shows that inventory and waiting dominate this stream.
AVAILABLE_SECONDS_PER_DAY = 27000
daily_demand = 450
queues = [4500, 1350, 900, 450]
cycle_times = [1, 39, 46, 62]
wait_days = sum(queue / daily_demand for queue in queues)
process_seconds = sum(cycle_times)
process_days = process_seconds / AVAILABLE_SECONDS_PER_DAY
lead_days = wait_days + process_days
print(f"Wait time: {wait_days:.2f} working days")
print(f"Process time: {process_seconds} seconds")
print(f"Lead time: {lead_days:.4f} working days")Check the result
Little's Law provides a useful cross-check:
\[ \text{Lead time} = \frac{\text{Work in process}}{\text{Throughput}} \]
The total mapped inventory is 7,200 units. At 450 units per day:
\[ 7{,}200 / 450 = 16 \text{ days} \]
This agrees with the wait-time total before adding process time. A mismatch can indicate missing inventory, inconsistent demand units, or a map boundary that does not match the calculation.
Interpret the timeline
A long wait-time bar indicates a queue or inventory problem. A long process-time bar indicates substantial touch time. These require different responses. Reducing a cycle time will not remove a queue if the queue is created by batch production, unreliable equipment, or uneven scheduling.
The timeline also prepares the map for future-state design. Mark the largest waits, then investigate whether they come from push production, batch sizes, rework, or uneven process capacity.
Exercise
A map has 3,000 units of inventory and demand of 600 units per day. The process steps add up to 120 seconds, and one working day has 24,000 available seconds. What are the wait time and lead time?
Show answer
Wait time is 3,000 / 600 = 5 working days. Process time is 120 / 24,000 = 0.005 working days, so lead time is 5.005 working days.