Sub topic 9
Information Flow and How Work Is Scheduled
Assume you already know how to identify the process steps and data boxes on a current-state map. This chapter focuses on the other half of the map: how information tells people what to make, move, or work on.
What information flow shows
Information flow is the path that carries demand, priorities, schedules, and status between the customer, the organization, production control, and process steps. It explains why work starts when it does.
A material-flow arrow answers, “Where does the item go?” An information-flow arrow answers, “Who tells this step what to do?”
A current-state map commonly includes these participants:
- The customer, who sends orders or demand signals.
- Sales or customer service, which receives and communicates demand.
- Production control or a planning team, which converts demand into a schedule.
- Suppliers, who receive orders for materials.
- Process steps, which receive instructions and report progress.
- A shipping or fulfillment step, which confirms completed delivery.
Use different visual conventions for different kinds of information. A straight arrow can represent a regular information flow. A jagged or lightning-shaped arrow can represent electronic communication if your mapping standard uses that symbol. Label the channel and frequency when they affect performance.
| Information | Sender | Receiver | Frequency |
|---|---|---|---|
| Weekly production schedule | Production control | Assembly | Weekly |
| Customer order changes | Customer service | Production control | As received |
| Material replenishment signal | Assembly | Warehouse | When the container is empty |
Trace the schedule from demand to work
Start with the customer and trace backward. Record how an order becomes an instruction at each process step.
Ask these questions at the point of work:
- Who decides what this process should make or handle?
- What system, message, board, or meeting provides that instruction?
- How often does the instruction change?
- What quantity and due date does it contain?
- How does the process report completion or problems?
- What happens when actual work differs from the schedule?
Do not assume that an enterprise planning system is the complete information flow. A supervisor may print a schedule, an operator may use a handwritten queue, and a warehouse may react to an empty container. Each of these mechanisms belongs on the map if it controls work.
The schedule may be sent to every process step. This is called push scheduling. Each step makes work according to a plan, then sends the result forward. Push scheduling can create excess work-in-process when upstream steps continue producing even though downstream steps are not ready.
A pull signal authorizes replenishment based on actual downstream consumption. A kanban is a pull signal, such as a card, bin, or electronic message, that specifies what quantity to replace. Pull does not mean that no schedule exists. It usually means that a schedule controls a selected point, while downstream consumption controls replenishment between connected steps.
Map the control pattern
Draw each schedule and signal on the current-state map, even when the pattern is inconsistent. Inconsistency often explains long queues.
For example, production control may send a weekly schedule to stamping, while assembly receives daily instructions. Stamping then produces a large batch to protect itself from future demand. The inventory between the steps is a visible result of the information pattern.
Record batch size, planning horizon, and update frequency. A weekly schedule with a five-day frozen period behaves differently from a schedule changed hourly. Frequent changes can cause expediting, setup interruptions, and conflicting priorities.
A useful current-state annotation identifies:
- The point where the main schedule enters the value stream.
- Every process that receives an independent schedule.
- Manual queues, priority lists, and unofficial work instructions.
- Delays between a demand change and a process response.
- Signals that reflect actual consumption rather than forecasts.
Exercise
Exercise
Assembly consumes 100 units from a supermarket each day. Stamping receives a weekly forecast and produces 500 units every Monday, regardless of assembly consumption. Is this pull flow?
Show answer
No. Assembly consumption may create a pull signal, but stamping is currently producing from a fixed forecast. Map the forecast as push scheduling and identify the supermarket and replenishment signal separately.