Sub topic 6
Drawing Process Boxes and Filling in Data Boxes
Assume you know the product family and the start and end points of the current-state map. You should also be comfortable with cycle time, inventory, customer demand, and simple rates. This chapter shows how to turn observations at each work area into consistent process and data boxes.
Build one process box for each major step
A process box represents a group of activities that share the same flow, operator group, equipment, and scheduling point. Name the box by the work performed, such as Stamping, Welding, Assembly, or Final inspection.
Do not create a box for every hand motion. Do not combine steps merely because they happen in the same building. If two steps have different queues, schedules, people, or performance, separate boxes usually reveal more useful information.
Place the boxes in material-flow order from left to right. Each process box should have a matching data box below or inside it. The process box answers “what happens here?” The data box answers “how does this step perform?”
Choose data that explains flow
A data box should contain facts that help explain capacity, delay, quality, or scheduling. Record the same core fields for every comparable process.
| Field | Meaning | Example |
|---|---|---|
| Cycle time (CT) | Time to complete one unit at the step | 39 seconds |
| Operators | People normally assigned to the step | 3 |
| Uptime or availability | Share of planned time the equipment can run | 88% |
| Changeover time | Time to switch between products or batches | 25 minutes |
| First-pass yield | Share completed correctly without rework | 97% |
Add fields only when they support the map’s purpose. Useful additions include batch size, queue size, downtime, rework rate, and working time per shift. Record the unit beside each value. “40” is ambiguous; “40 seconds per unit” is usable.
Use observed values from the point of work. If performance varies, record a representative value and note the range or sampling period. For example, write CT 39 s, observed range 35–48 s rather than presenting a short observation as a permanent truth.
Keep definitions consistent
Cycle time is the elapsed time between completed units at one process. It is not automatically the same as touch time, setup time, or total time in the department. If several operators work in parallel, state whether the value is the time for one unit through the process or the effective output interval for the whole step.
Available time must also be defined consistently. State whether breaks, meetings, planned maintenance, and changeovers are included. These definitions affect comparisons with takt time later.
Use a small data sheet while walking the process, then transfer verified values to the map. Separate facts from assumptions with a note such as source: 30-unit observation or source: supervisor estimate.
steps = [
{"name": "Stamping", "cycle_s": 1, "operators": 2, "uptime": 0.92},
{"name": "Welding", "cycle_s": 39, "operators": 3, "uptime": 0.88},
{"name": "Assembly", "cycle_s": 46, "operators": 4, "uptime": 0.95},
]
for step in steps:
effective_capacity = step["uptime"] / step["cycle_s"]
print(f"{step['name']}: {effective_capacity:.3f} completed units per second")Check the completed boxes
Before calculating totals, verify that:
- Every process in the physical flow has one process box.
- Each box uses the same units and time basis.
- Queue sizes appear between the correct process steps.
- Cycle times describe the same kind of interval.
- Estimates and observed values are labeled.
- The data supports the question the map is meant to answer.
Exercise
A welding step has a 39-second cycle time, three operators, and a 25-minute changeover. Which values belong in its data box?
Show answer
Record all three values with units: CT 39 s, operators 3, and changeover 25 min. Also label the source and observation period if known.