The Risks of Fast-Tracking: Rework and Coordination
Assume you can read a simple activity network and understand predecessors, successors, and project duration. You should also know that the critical path is the longest path through the network. This chapter focuses on what can go wrong when you shorten a schedule by changing dependencies.
What fast-tracking changes
Fast-tracking is a schedule compression technique. It shortens the project by overlapping activities that were originally planned in sequence.
For example, design may normally finish before construction starts. Fast-tracking lets construction start while the final design work is still in progress. The schedule becomes shorter, but the construction team may begin with incomplete information.
design = 6
build = 8
build_start = 3 # Build starts three days before design finishes
sequential_finish = design + build
fast_track_finish = max(design, build_start + build)
nominal_saving = sequential_finish - fast_track_finish
print(f"Sequential finish: {sequential_finish} days")
print(f"Fast-tracked finish: {fast_track_finish} days")
print(f"Nominal saving: {nominal_saving} days")This example reports a nominal saving of three days. Nominal means the saving exists in the planned schedule. It does not account for redesign, delays, extra meetings, or other effects caused by the overlap.
Why overlap creates rework
Rework is work that must be repeated or corrected because an earlier result changed, was incomplete, or contained an error.
Suppose a design team releases preliminary equipment dimensions. A construction team uses those dimensions to install supports. Later, the design team changes the equipment. The supports may need to be removed and rebuilt. The original schedule saving can disappear.
Fast-tracking creates rework risk when:
- The earlier activity has unstable requirements.
- The later activity depends on details that are not finished.
- Changes are expensive to undo.
- Quality checks occur after work has already started.
- Different teams use different versions of the same information.
Rework is not always a reason to reject fast-tracking. The decision depends on its expected effect. A small chance of inexpensive correction may be acceptable when a deadline has high value. A small chance of rebuilding a critical structure may be unacceptable.
Coordination cost
Coordination cost is the time and effort needed to keep people, decisions, and information aligned. Overlap increases this cost because teams can no longer rely on a simple handoff.
The project may need:
- More frequent design and construction meetings.
- A named person to approve changes quickly.
- A shared document and version-control process.
- Clear rules for which information is ready for use.
- Short response times for questions and decisions.
- A record of assumptions and unresolved issues.
Without these controls, teams may act on different information. One team may build from revision 3 while another team is already using revision 4. The resulting conflict can create both rework and delay.
Dependencies, leads, and boundaries
A dependency describes how one activity relates to another. In a finish-to-start dependency, the successor starts after the predecessor finishes. Fast-tracking changes this relationship by introducing a lead.
A lead allows the successor to start before the predecessor is complete. The lead must have a clear boundary. For example, construction may start for the foundation after the foundation design is approved, while upper-floor construction waits for later design details.
Do not treat a lead as permission to ignore the predecessor. Identify the part of the work that is stable enough to begin and the part that must remain blocked.
| Question | Safer fast-tracking practice |
|---|---|
| What information is incomplete? | List the missing decisions and their owners. |
| What work can change? | Start only work with a low cost of reversal. |
| How will changes be controlled? | Use versioned documents and formal approvals. |
| What happens if a change arrives? | Reserve time and budget for correction. |
Managing the risk
Evaluate fast-tracking before changing the schedule baseline. Estimate the likely saving, the probability of rework, the cost of rework, and the coordination effort. Then compare the expected benefit with the expected cost and risk.
A useful control is a hold point. A hold point is a planned decision gate where work pauses until required information is approved. Hold points limit the overlap to areas where uncertainty is manageable.
Fast-tracking is strongest when work can be divided into independent portions. It is weaker when every part depends on one final decision or when errors are costly to reverse.
Exercise
Design takes 10 days and construction takes 12 days. Construction starts on day 7, but a design change causes 4 days of rework during construction. What is the nominal saving, and what is the saving after rework?
Show answer
The sequential duration is 22 days. Fast-tracking finishes on day 19, so the nominal saving is 3 days. Four days of rework removes that saving and creates a 1-day increase compared with the sequential plan.