Float and Near-Critical Paths
What you should already know
Assume you can read a simple activity network, identify activity durations and dependencies, and calculate with days and costs. This chapter uses the critical path method. The critical path is the longest dependency path through a project network. It determines the shortest possible project duration.
Float, also called slack, is the amount of time an activity can move later without causing a defined delay. A project can have several paths. Activities on the critical path have zero total float. Activities on other paths may have some room, but that room can disappear as the schedule changes.
A sample network
Consider this network:
The main paths are:
- A-B-D-F: 3 + 4 + 2 + 1 = 10 days
- A-C-D-F: 3 + 6 + 2 + 1 = 12 days
- A-C-E-F: 3 + 6 + 3 + 1 = 13 days
The project duration is 13 days. Therefore, A-C-E-F is the critical path. A-B-D-F is near-critical because it is only three days shorter than the project duration.
Calculating activity float
The critical path method uses four dates:
- Early start (ES) is the earliest time an activity can start.
- Early finish (EF) is the earliest time an activity can finish.
- Late start (LS) is the latest time an activity can start without delaying the project.
- Late finish (LF) is the latest time an activity can finish without delaying the project.
For an activity with duration d:
- EF = ES + d
- LS = LF - d
- Total float = LS - ES, or LF - EF
A forward pass calculates early dates from the beginning of the network. A backward pass calculates late dates from the planned project finish.
| Activity | Duration | ES | EF | LS | LF | Total float | Free float |
|---|---|---|---|---|---|---|---|
| A | 3 | 0 | 3 | 0 | 3 | 0 | 0 |
| B | 4 | 3 | 7 | 6 | 10 | 3 | 2 |
| C | 6 | 3 | 9 | 3 | 9 | 0 | 0 |
| D | 2 | 9 | 11 | 10 | 12 | 1 | 1 |
| E | 3 | 9 | 12 | 9 | 12 | 0 | 0 |
| F | 1 | 12 | 13 | 12 | 13 | 0 | 0 |
Total float and free float
Total float measures how much an activity can move without delaying the project finish. Activity B has three days of total float. It could finish as late as day 10, while the project can still finish on day 13.
Free float is more local. It measures how much an activity can move without delaying the early start of any immediate successor. B has two days of free float because D can still start at day 9 if B finishes at day 9.
An activity can have total float but no free float. This happens when delaying it does not delay the project finish, but it does delay a successor's earliest possible start.
Managing near-critical paths
A near-critical path has little total float. There is no universal cutoff. A team might classify any path with one or two days of float as near-critical, depending on the project's size and uncertainty.
Near-critical paths matter because small changes can make them critical:
- A delay on a near-critical activity consumes its float.
- A delay on a critical activity may make a near-critical path the longest path.
- Crashing or fast-tracking one critical path can expose another path.
- Shared activities can affect several paths at once.
For this reason, schedule analysis should track paths, not only individual activities. After an approved change, recalculate early dates, late dates, float, and the critical path. Do not assume the original critical path remains critical throughout the project.
Practical review
When reviewing a schedule:
- Calculate the project duration and critical path.
- Record total and free float for activities with nonzero float.
- Mark paths with little float for closer monitoring.
- Check whether resource limits, calendars, or delays consume the calculated float.
- Recalculate after changing durations or dependencies.
Exercise
In the sample network, activity B finishes on day 7 and has an early successor start of day 9. What are B's total float and free float, and why are they different?
Show answer
B has three days of total float because its late finish is day 10. It has two days of free float because delaying B beyond day 9 would delay D's early start, even though the project could still finish by day 13.