Crashing: Trading Cost for Time
Assume you can read a simple activity network, calculate durations and costs, and identify basic project-management terms such as scope, schedule, and resources. This chapter focuses on crashing, a schedule-compression technique that shortens project duration by adding resources or paying for faster work.
What Crashing Means
Crashing changes how quickly an activity is completed without changing the activity's scope. For example, a team might add workers, approve overtime, rent additional equipment, or use a faster supplier.
Crashing does not mean shortening every activity. An activity can shorten the project only when it is on the current critical path, the longest chain of dependent activities that determines the project finish date.
Consider this network:
The two paths are:
- A-B-D: 3 + 5 + 3 = 11 days
- A-C-D: 3 + 4 + 3 = 10 days
The first path is critical. Shortening activity C by one day does not shorten the project. The A-B-D path still takes 11 days.
Crash Cost Slope
Each activity has a normal duration and a crash duration. The crash duration is the shortest practical duration under defined conditions. The additional cost of reducing the duration is the crash cost.
The crash cost slope is the additional cost for each day removed:
\[ \text{Crash cost slope} = \frac{\text{Crash cost} - \text{Normal cost}} {\text{Normal duration} - \text{Crash duration}} \]
For example, an activity with a normal cost of 2,000, a crash cost of 2,800, a normal duration of 5 days, and a crash duration of 3 days has this slope:
\[ \frac{2,800 - 2,000}{5 - 3} = 400 \]
Each crashed day costs 400 on average.
| Activity | Normal duration | Minimum duration | Cost per crashed day |
|---|---|---|---|
| A | 3 days | 2 days | 500 |
| B | 5 days | 3 days | 400 |
| C | 4 days | 3 days | 300 |
| D | 3 days | 2 days | 600 |
A low slope does not automatically make an activity the best choice. The activity must also be on the current critical path and still have crashable time.
Crashing Step by Step
Use this procedure:
- Calculate the current duration and identify every critical path.
- List critical-path activities that can still be shortened.
- Calculate or confirm each activity's crash cost slope.
- Choose the least expensive option that actually shortens the project.
- Reduce that activity by one day, or by the smallest practical increment.
- Recalculate the network. The critical path may change.
- Stop when the target date is met, no activity can be shortened, or the next reduction costs more than the benefit.
For the network above, B is on the critical path and costs 400 per day to crash. Reducing B from 5 to 4 days changes the project duration from 11 to 10 days. Activity A is also on the critical path and costs 500 per day. Reducing A from 3 to 2 days changes the duration from 10 to 9 days.
The total crash cost is 400 + 500 = 900. Crashing C first would be cheaper per day, but it would not reduce the project duration at that point.
activities = {
"A": {"dur": 3, "min": 2, "slope": 500, "preds": []},
"B": {"dur": 5, "min": 3, "slope": 400, "preds": ["A"]},
"C": {"dur": 4, "min": 3, "slope": 300, "preds": ["A"]},
"D": {"dur": 3, "min": 2, "slope": 600, "preds": ["B", "C"]},
}
def project_duration(durs):
finish = {}
for name, activity in activities.items():
start = max((finish[p] for p in activity["preds"]), default=0)
finish[name] = start + durs[name]
return max(finish.values())
durs = {name: activity["dur"] for name, activity in activities.items()}
target = 9
spent = 0
while project_duration(durs) > target:
now = project_duration(durs)
options = []
for name, activity in activities.items():
if durs[name] > activity["min"]:
trial = {**durs, name: durs[name] - 1}
if project_duration(trial) < now:
options.append((activity["slope"], name))
if not options:
break
slope, name = min(options)
durs[name] -= 1
spent += slope
print(f"crash {name}: {now} -> {project_duration(durs)} days")
print(f"duration {project_duration(durs)} days, crash cost {spent}")Limits and Errors
Crashing has a practical limit. A team cannot reduce an activity below its minimum duration without changing its method, scope, quality, or risk. Added resources can also create coordination problems or reduce productivity.
Recalculate after every change. Crashing one activity can create a second critical path. If two critical paths have equal length, shortening only one path may no longer shorten the project. You may need to crash an activity on both paths at the same time.
Exercise
In the example network, why is crashing activity C from 4 to 3 days not the first useful action, even though C has the lowest crash cost slope?
Show answer
C is not on the current critical path. Shortening C leaves the A-B-D path at 11 days, so the project finish date does not change.