Sub topic 7
Crashing Step by Step, One Day at a Time
Assume you can read a simple activity network, identify predecessors, and do basic duration and cost arithmetic. You should also know that the critical path is the longest path through the network. Its duration determines the project finish date.
What crashing changes
Crashing shortens an activity by adding resources or spending more money. Examples include assigning another worker, authorizing overtime, renting faster equipment, or purchasing an expedited service.
Crashing does not automatically shorten the project. Only a reduction on a current critical path can reduce the overall project duration. Reducing an activity with available float may use up that float without changing the finish date.
A safe crashing decision has four parts:
- Confirm the current critical path.
- List activities on that path that can still be shortened.
- Compare their additional cost per day.
- Crash one day, then recalculate the network.
The fourth step matters because the critical path can change after every reduction.
Crash cost slope and limits
The crash cost slope is the extra cost for reducing an activity by one day:
\[ \text{Crash cost slope} = \frac{\text{Crash cost} - \text{Normal cost}} {\text{Normal duration} - \text{Crash duration}} \]
If an activity normally costs $2,000 and normally takes 5 days, but it can be completed in 3 days for $2,800, its slope is:
\[ \frac{2,800 - 2,000}{5 - 3} = 400 \]
Each shortened day costs $400, assuming the cost is linear.
The crash limit is the shortest feasible duration. You cannot keep crashing an activity after it reaches this limit. A limit may come from physical constraints, resource availability, safety rules, or the time needed for the work itself.
| Activity | Normal duration | Minimum duration | Extra cost per day |
|---|---|---|---|
| B | 5 days | 3 days | $400 |
| A | 3 days | 2 days | $500 |
| D | 3 days | 2 days | $600 |
The one-day crashing procedure
Use this loop:
flowchart TD
A[Calculate current project duration] --> B[Find the current critical path]
B --> C[List crashable activities on every critical path]
C --> D{Any useful option?}
D -- No --> E[Stop or revise the target]
D -- Yes --> F[Choose the lowest-cost valid day]
F --> G[Reduce that activity by one day]
G --> AAt each iteration, distinguish between cost-effective and merely possible reductions. A cheap activity is not a good choice if it has float and does not shorten the project. Test each candidate by reducing its duration temporarily and recalculating the finish date.
Consider this network:
- A takes 3 days.
- B follows A and takes 5 days.
- C follows A and takes 4 days.
- D follows both B and C and takes 3 days.
The two main paths are A-B-D, which takes 11 days, and A-C-D, which takes 10 days. Therefore, A-B-D is critical.
activities = {
"A": {"dur": 3, "min": 2, "slope": 500, "preds": []},
"B": {"dur": 5, "min": 3, "slope": 400, "preds": ["A"]},
"C": {"dur": 4, "min": 3, "slope": 300, "preds": ["A"]},
"D": {"dur": 3, "min": 2, "slope": 600, "preds": ["B", "C"]},
}
def project_duration(durs):
finish = {}
for name, activity in activities.items():
start = max((finish[p] for p in activity["preds"]), default=0)
finish[name] = start + durs[name]
return max(finish.values())
durs = {name: activity["dur"] for name, activity in activities.items()}
target = 9
spent = 0
while project_duration(durs) > target:
current = project_duration(durs)
options = []
for name, activity in activities.items():
if durs[name] > activity["min"]:
trial = {**durs, name: durs[name] - 1}
if project_duration(trial) < current:
options.append((activity["slope"], name))
if not options:
break
slope, name = min(options)
durs[name] -= 1
spent += slope
print(f"crash {name}: {current} -> "
f"{project_duration(durs)} days, +{slope}")
print(f"duration {project_duration(durs)} days, crash cost {spent}")The first useful reduction is one day from B. The project falls from 11 to 10 days, at a cost of $400. After recalculating, B remains the cheapest useful option and can be reduced one more day. The project then reaches 9 days, with a total crash cost of $800.
Common errors
- Choosing the cheapest activity without testing it: C is cheaper than B, but initially it is not on the critical path and does not shorten the project.
- Using the original critical path throughout: After each crash, recalculate path lengths. A different path may become critical.
- Crashing beyond the minimum duration: The crash limit is a real constraint, not a suggestion.
- Ignoring multiple critical paths: If two paths have the same longest duration, shortening only one path may not change the project finish.
- Treating the slope as the whole decision: Consider quality, safety, resource conflicts, and whether the added resources create new coordination work.
Exercise
A project has two critical paths. Activity X appears on both paths and costs $700 per day to crash. Activity Y appears on only one path and costs $300 per day. Which activity should be considered first, and why?
Show answer
Consider X first. Crashing Y alone may leave the other critical path unchanged, so the project may not finish earlier. X can reduce both critical paths, although you should still test its duration limit and other constraints.