Sub topic 9
Fast-Tracking: Doing Work in Parallel
This chapter assumes you can read a simple activity network, identify its critical path, and distinguish finish-to-start dependencies from other dependency types.
What fast-tracking changes
Fast-tracking is a schedule-compression technique that overlaps activities that were originally planned in sequence. It reduces elapsed time without necessarily reducing the duration of either activity.
For example, design may normally finish before construction begins:
- Design: days 0–6
- Build: days 6–14
- Project duration: 14 days
With fast-tracking, construction can begin on approved design sections at day 3:
- Design: days 0–6
- Build: days 3–11
- Project duration: 11 days
The schedule gains three days because the activities run partly in parallel. The build activity still takes eight days.
design, build = 6, 8
sequential = design + build
build_start = 3
overlapped = max(design, build_start + build)
print(f"Sequential finish: day {sequential}")
print(f"Fast-tracked finish: day {overlapped}")
print(f"Time saved: {sequential - overlapped} days")The calculation assumes that work can start safely and productively before all design work is complete. That assumption must be checked rather than treated as a guaranteed saving.
Changing a dependency
Fast-tracking usually changes a finish-to-start relationship. In a finish-to-start dependency, Activity B cannot start until Activity A finishes. Fast-tracking replaces that strict relationship with a partial or staged dependency.
For instance, a design team might release foundation drawings before completing interior drawings. Foundation work can then begin while the remaining design continues.
The dependency is no longer simply “all design finished, then build.” It becomes “the required design package finished, then the corresponding build work starts.” This creates more detailed coordination requirements.
Leads and staged work
A lead allows a successor activity to start before its predecessor is fully complete. For example, a two-day lead on a ten-day design activity permits the next activity to start two days before design finishes.
Leads are useful only when the predecessor produces usable outputs in stages. They are unsafe when the successor depends on the predecessor's final result.
Break large activities into handoff points when possible:
- Identify a deliverable that can be completed independently.
- Define the information the successor needs.
- Set a review and approval point.
- Start the successor only after that handoff is accepted.
- Track changes that could affect work already started.
This approach is more reliable than simply changing a schedule relationship from finish-to-start to start-to-start.
Risks of overlapping work
Fast-tracking transfers schedule pressure into coordination and technical risk. Common risks include:
- Rework when an unfinished design changes completed work.
- Waiting when an expected design package is late.
- Conflicts between teams working in the same area.
- More inspections, meetings, and interface decisions.
- Reduced flexibility when a late decision affects several active activities.
The schedule gain should therefore include an allowance for likely rework. A nominal three-day gain may be only one day after redesign, removal, and reconstruction.
> callout warning > Fast-tracking does not make work finish sooner by itself. It starts some work sooner, while increasing the chance that the work must be changed.
When fast-tracking is suitable
Fast-tracking is a stronger option when:
- Work can be divided into independent sections.
- Early deliverables are stable and reviewable.
- Teams can communicate frequently.
- Rework is inexpensive and reversible.
- The activities are on the critical path or are likely to become critical.
It is a poor option when work is tightly coupled, safety-critical, difficult to inspect, or expensive to undo. It also cannot shorten the project if the overlap occurs entirely on an activity with float and does not affect the finish date.
Measure the real gain
Compare the original and overlapped schedules, then record the assumptions behind the overlap. Include expected rework, review time, and coordination effort in the decision. If those costs or risks become unacceptable, restore the original dependency or use a smaller overlap.
Exercise
Design takes six days and build takes eight days. Build starts on day 3 instead of day 6. What is the planned project duration and nominal time saving?
Show answer
Build finishes on day 11, so the planned duration is 11 days and the nominal saving is 3 days. This excludes any rework or coordination delay.