Sub topic 8
Dependency Types and Leads
This chapter assumes you can read a simple activity network or Gantt chart and know basic project terms such as activity, duration, predecessor, successor, scope, cost, and resource. You also need basic arithmetic with dates and durations.
A dependency is a relationship that controls when one activity can start or finish relative to another. The earlier activity is the predecessor. The later activity is the successor. For example, “design the screen” may be a predecessor of “build the screen.”
The four dependency types
Project scheduling software usually represents a dependency with two letters. The first letter describes the predecessor event. The second describes the successor event.
| Type | Meaning | Example |
|---|---|---|
| Finish-to-start (FS) | The successor starts after the predecessor finishes | Build starts after design finishes |
| Start-to-start (SS) | The successor starts after the predecessor starts | Testing starts after coding starts |
| Finish-to-finish (FF) | The successor finishes after the predecessor finishes | Documentation finishes after development finishes |
| Start-to-finish (SF) | The successor finishes after the predecessor starts | A new support shift starts before the old shift finishes |
Finish-to-start is the most common relationship. It creates the simple rule, “Activity B cannot start until Activity A is complete.”
The other relationships allow work to overlap while preserving a logical connection. For example, a test team may begin testing completed modules while developers continue coding later modules. That relationship can be modeled as start-to-start, often with a lag.
Reading dependencies on a timeline
Consider a design activity that lasts six days and a build activity that lasts eight days.
With a finish-to-start dependency, build begins after design ends:
- Design: days 1–6
- Build: days 7–14
- Project duration: 14 days
With a start-to-start dependency and a two-day lag, build starts two days after design starts:
- Design: days 1–6
- Build: days 3–10
- Project duration: 10 days
The dependency has changed the amount of allowed overlap. The project finishes sooner, but the build team may need partial design information before the full design is approved.
Leads and lags
A lag is a planned waiting period between linked activities. Suppose inspection must occur two days after installation finishes because the equipment needs to settle. The schedule can use an FS dependency with a two-day lag:
- Installation finishes on day 6.
- Inspection starts on day 9.
- Days 7 and 8 are the two-day lag.
A lead allows the successor to begin before the predecessor has fully finished. In scheduling software, a lead is often entered as a negative lag. An FS relationship with a three-day lead means the successor starts three days before the predecessor finishes.
For the design and build example:
- Design lasts six days.
- Build lasts eight days.
- FS with a three-day lead means build starts on day 4, while design continues through day 6.
- Build finishes on day 11.
- The project gains three days compared with the original 14-day sequence.
A lead is one way to describe fast-tracking. It does not remove the dependency. It changes when the successor is allowed to begin.
Choosing the relationship carefully
Use the relationship that represents the real work, not the one that produces the shortest schedule.
- Use FS when the successor needs the predecessor fully complete.
- Use SS when both activities can progress together after the predecessor begins.
- Use FF when the completion of one activity controls the completion of another.
- Use SF only for unusual handoffs, such as replacing an operating shift.
- Use a lag for a real waiting period, such as curing, shipping, or review time.
- Use a lead when planned overlap is possible and the added coordination or rework risk is accepted.
A lead can shorten the schedule without adding people, as crashing does. However, it may increase uncertainty and coordination work. Before applying one, identify what information the successor needs, when that information becomes reliable, and who approves changes.
Exercise
Design lasts 5 days and build lasts 7 days. Build uses an FS dependency with a 2-day lead. On which day does build start, and when does the project finish if design starts on day 1?
Show answer
Design finishes at the end of day 5. A 2-day lead starts build two days before design finishes, on day 4. Build runs through day 10, so the project finishes on day 10.