Sub topic 6
Crash Cost Slope and Crash Limits
Assume you can read a simple activity network, identify the critical path, and calculate basic durations and costs. This chapter focuses on how to measure the cost of shortening an activity and how to recognize when further shortening is impossible or uneconomical.
What the crash cost slope measures
An activity usually has two planned duration and cost points:
- Normal duration is the time needed under ordinary conditions.
- Normal cost is the cost at that duration.
- Crash duration is the shortest practical duration.
- Crash cost is the cost of reaching that shortest duration.
The crash cost slope is the extra cost for shortening an activity by one time unit:
\[ \text{Crash cost slope} = \frac{\text{Crash cost} - \text{Normal cost}} {\text{Normal duration} - \text{Crash duration}} \]
A slope of $500 per day means that each day removed from the activity adds $500, assuming the cost is linear between the two limits.
| Activity | Normal duration | Crash duration | Normal cost | Crash cost | Slope |
|---|---|---|---|---|---|
| A | 3 days | 2 days | $1,200 | $1,700 | $500/day |
| B | 5 days | 3 days | $3,000 | $3,800 | $400/day |
| C | 4 days | 3 days | $2,000 | $2,300 | $300/day |
For activity A:
\[ \frac{1{,}700 - 1{,}200}{3 - 2} = \frac{500}{1} = \$500 \text{ per day} \]
The slope is a marginal cost. It tells you the cost of the next day you remove, not the total cost of the activity.
Crash limits
The crash limit is the maximum amount by which an activity can be shortened:
\[ \text{Maximum reduction} = \text{Normal duration} - \text{Crash duration} \]
Activity B can be reduced by two days. After those two reductions, its duration is three days. You cannot reduce it further using the same approved method.
A crash limit can result from:
- The minimum time required by a technical process.
- The maximum number of workers or machines available.
- Safety or quality requirements.
- A fixed delivery or curing time.
- A dependency that prevents earlier work.
- A cost that becomes unreasonable beyond the stated limit.
The crash duration is a planning assumption, not a promise. A team may discover that the assumed minimum is infeasible after checking resources, permits, safety controls, or supplier capacity.
activities = {
"A": {"normal": 3, "crash": 2, "normal_cost": 1200, "crash_cost": 1700},
"B": {"normal": 5, "crash": 3, "normal_cost": 3000, "crash_cost": 3800},
"C": {"normal": 4, "crash": 3, "normal_cost": 2000, "crash_cost": 2300},
}
for name, activity in activities.items():
reduction = activity["normal"] - activity["crash"]
slope = (activity["crash_cost"] - activity["normal_cost"]) / reduction
print(
f"{name}: up to {reduction} day(s), "
f"${slope:,.0f} extra per day"
)Why the cheapest slope is not always the right choice
Crash slope helps compare alternatives, but it does not identify activities that can shorten the project. Only an activity on the current critical path can reduce the project finish date.
For example, activity C may have a slope of $300 per day, but crashing C has no project benefit if it has two days of float. Its early finish would only create more unused float. A more expensive critical activity may be the better choice.
After every crash decision:
- Reduce one activity by one day, or by the approved increment.
- Recalculate the network.
- Identify the new critical path.
- Check whether another path has become critical.
- Recalculate the remaining crash limits and costs.
Crashing one path can create multiple critical paths. If two paths now control the finish date, shortening only one of them will not shorten the project. You may need to crash a shared activity or crash activities on both paths.
When to stop crashing
Stop when the target date is reached, or when every remaining option is infeasible or provides too little value. A project may also stop before the technical crash limit when the extra cost exceeds the benefit of finishing earlier.
Track both measures:
- Time gained: the actual reduction in project duration.
- Incremental crash cost: the extra cost for that reduction.
If a one-day crash costs $400 but avoids only $200 of delay penalties, it is usually not worthwhile unless another business benefit justifies it. Also include indirect effects such as overtime fatigue, defects, rework, and added supervision.
Exercise
Activity X has a normal duration of 8 days and cost of $4,000. Its crash duration is 6 days and crash cost is $5,200. What are its crash cost slope and maximum reduction?
Show answer
The maximum reduction is 2 days. The slope is ($5,200 - $4,000) / (8 - 6) = $600 per day.