Sub topic 1
Activities, Durations and Dependencies in a Schedule Network
A schedule network shows the order in which project activities can happen. Each activity has a duration, and each dependency states when one activity may start in relation to another. Together, these facts describe the project’s possible flow from start to finish.
This chapter assumes that you can read a simple Gantt chart or activity network and understand basic project terms such as scope, cost, resources, and schedule.
Prerequisites
You should be able to:
- Add and compare durations.
- Identify whether one activity must happen before another.
- Read a simple table or diagram.
- Distinguish planned work from project milestones.
Activities and durations
An activity is a defined piece of work that produces an output or moves the project forward. Examples include “design database,” “install equipment,” and “test the application.”
A duration is the amount of working time planned for an activity. It may be measured in hours, days, or weeks. A duration is not the same as effort. Effort is the total labor required, while duration is the elapsed time on the calendar.
For example, two people might complete 16 hours of effort in one working day. If one person performs the same work, it might take two days. The activity’s duration depends on both the work and the available resources.
A schedule commonly represents activities like this:
| Activity | Description | Duration | Immediate predecessors |
|---|---|---|---|
| A | Gather requirements | 3 days | None |
| B | Design solution | 4 days | A |
| C | Prepare test data | 2 days | A |
| D | Run acceptance testing | 3 days | B and C |
An immediate predecessor is an activity that must finish before the listed activity can begin. Activity A has no predecessor, so it can start at the beginning. Activity D has two predecessors, so both B and C must finish before D starts.
Dependencies define the network
A dependency is a relationship between activities. It limits the order in which work can occur. The most common relationship is finish-to-start: the predecessor must finish before the successor starts.
In the example, the network is:
The arrows show constraints, not necessarily continuous work. After A finishes, B and C may start independently. D must wait for both branches.
A network can contain parallel work. Parallel work reduces elapsed time when activities do not depend on one another. In this example, B and C can overlap:
- A finishes after day 3.
- B runs from day 3 to day 7.
- C runs from day 3 to day 5.
- D waits for B, because B finishes later.
- D runs from day 7 to day 10.
The project duration is therefore 10 working days, not 12. Adding every activity duration would incorrectly assume that B and C run one after another.
Finding earliest dates
To calculate an activity’s earliest start, find the latest earliest finish among its predecessors. An activity with no predecessors starts at time zero.
For each activity:
- Set its earliest start to zero if it has no predecessors.
- Otherwise, use the greatest predecessor finish time.
- Add the activity duration to get its earliest finish.
- Continue in dependency order.
For the network above:
| Activity | Earliest start | Duration | Earliest finish |
|---|---|---|---|
| A | 0 | 3 | 3 |
| B | 3 | 4 | 7 |
| C | 3 | 2 | 5 |
| D | 7 | 3 | 10 |
The project’s earliest possible finish is the greatest finish time of its ending activities. Here, D finishes at day 10.
Checking a network before compression
Schedule compression changes how quickly work finishes. Before considering it, verify the network:
- Confirm that every activity has a clear deliverable.
- Check that durations use the same calendar units.
- Confirm that each dependency reflects a real handoff, approval, or technical constraint.
- Look for missing predecessors and accidental circular dependencies.
- Identify activities that can run in parallel.
- Record assumptions about weekends, holidays, and resource availability.
These checks matter because an incorrect dependency can make a project appear longer or shorter than it really is. Later schedule-compression decisions depend on this network model.
Exercise
Activities A, B, and C have durations of 2, 5, and 3 days. B and C both depend on A, and D takes 2 days after both B and C finish. What is the earliest project finish?
Show answer
A finishes on day 2. B finishes on day 7 and C finishes on day 5. D must wait for B, so it finishes on day 9.