Sub topic 11
Choosing Between Crashing and Fast-Tracking
Prerequisites and decision context
This chapter assumes that you can read a simple activity network, identify durations and dependencies, and perform basic cost calculations. You should also understand the critical path, which is the longest sequence of dependent activities that determines the project finish date. Float is the time an activity can slip without delaying that finish date.
Schedule compression shortens the planned project duration without reducing scope. The two main techniques are:
- Crashing, which adds resources or pays for other changes to shorten an activity.
- Fast-tracking, which overlaps activities that were originally planned in sequence.
Choose a technique only after confirming the required finish date, available budget, acceptable risk, and technical constraints.
How the techniques change a schedule
Crashing changes the duration of an activity. For example, adding a second work crew may shorten installation from six days to four. The dependency remains finish-to-start, but the predecessor finishes sooner.
Fast-tracking changes the relationship between activities. A successor starts before its predecessor is fully complete. This creates a lead, which is an intentional overlap between two activities.
A noncritical activity usually cannot shorten the project. If the activity has two days of float, reducing it by one day uses float but does not move the project finish. The same is true when fast-tracking a relationship that is not on the critical path.
Comparing cost, risk, and schedule gain
Crashing has a visible direct cost. Its crash cost slope estimates the cost of removing one day:
\[ \text{Crash cost slope} = \frac{\text{Crash cost} - \text{Normal cost}} {\text{Normal duration} - \text{Crash duration}} \]
For example, an activity with a normal cost of $4,000 and duration of six days, and a crash cost of $5,000 and duration of four days, has a slope of $500 per day.
Fast-tracking may have little immediate cost, but it increases uncertainty. Design changes can require construction rework. Incomplete requirements can cause testing to be repeated. More handoffs also increase coordination effort.
| Decision factor | Crashing | Fast-tracking |
|---|---|---|
| Main change | Shortens selected activities | Overlaps dependent activities |
| Direct cost | Usually higher and measurable | May be lower at first |
| Main risk | Overtime, resource limits, reduced productivity | Rework, defects, and coordination failures |
| Best fit | Work that can use more resources or a faster method | Work with stable interfaces and recoverable overlap |
| Control method | Track cost and actual duration | Track assumptions, changes, and rework |
A practical selection procedure
Use this sequence when comparing options:
- Confirm how many calendar days must be saved.
- Recalculate the critical path and identify near-critical paths.
- List crashable activities and their cost slopes.
- Identify dependencies that could safely accept overlap.
- Estimate fast-tracking rework, coordination, and approval risks.
- Compare the total expected cost, not only the visible cost.
- Apply the smallest change that meets the target.
- Recalculate the network after every change.
A greedy crashing approach chooses the cheapest critical activity that reduces the project duration. This approach is useful for a small network, but it is not always globally optimal. After one activity is shortened, another path may become critical. The cheapest next option may then be different.
design, build = 6, 8
sequential = design + build
# Build starts three days before design is complete.
build_start = 3
overlapped = max(design, build_start + build)
print(f"Sequential finish: {sequential} days")
print(f"Fast-tracked finish: {overlapped} days")
print(f"Schedule gain: {sequential - overlapped} days")This example saves three days by starting build on day three. It assumes that build can begin with incomplete design information. The calculation does not include possible rework, so the schedule gain is only a planning estimate.
Limits and combined strategies
Both techniques have limits. An activity may already be at its minimum practical duration. Additional people may create communication overhead instead of saving time. Some activities cannot overlap because of safety, legal approval, physical access, or information dependencies.
A combined strategy can work well. For example, fast-track design and procurement while crashing a critical installation activity. Recalculate the network after each step, because compression can create a new critical path or remove the expected benefit.
Exercise
A project needs to save two days. A critical activity can be crashed for $600 per day. A noncritical activity has three days of float and can be shortened for $200 per day. Which option should be considered first, and why?
Show answer
Consider crashing the critical activity. Shortening the noncritical activity would use float but would not shorten the project finish, unless the network changes.