Sub topic 12
Limits, Diminishing Returns and Combining Techniques
This chapter assumes you can read a simple activity network or Gantt chart, identify a critical path, and calculate basic duration and cost changes. Schedule compression shortens the project without changing its scope. Crashing and fast-tracking can help, but neither can remove every schedule constraint.
Why compression has limits
A project has a shortest practical duration. Some work cannot start until a required result exists. Other work cannot be shortened beyond its crash limit, even with more people or equipment.
Common limits include:
- An activity reaches its minimum feasible duration.
- The required skill, equipment, or workspace is unavailable.
- Extra workers create communication overhead instead of saving time.
- A safety, testing, approval, or curing period cannot be shortened.
- Fast-tracking creates too much rework or coordination.
- The project has multiple critical paths that must all be shortened.
- The deadline requires more compression than the network can support.
A crash limit is the shortest duration an activity can achieve under realistic conditions. A fast-track limit is the greatest safe overlap between activities. These limits should be recorded before choosing a target date.
Diminishing returns
Diminishing returns occur when each additional unit of compression produces less useful schedule gain, costs more, or adds more risk.
For example, crashing a critical activity by one day may shorten the project by one day. After that change, another path may become critical. Crashing the same activity again might no longer shorten the project because the new critical path controls the finish.
Fast-tracking also has diminishing returns. The first overlap may be safe because the later team can use stable early information. A larger overlap may force the team to redo completed work when that information changes.
A useful decision compares the marginal result of the next change:
| Option | Direct effect | Main cost or risk | Use when |
|---|---|---|---|
| Crash one critical activity | May remove one project day | Higher direct cost | Resources are available and the activity has crash capacity |
| Crash activities on parallel critical paths | May remove one project day | Cost multiplies across paths | Several paths have equal controlling duration |
| Fast-track two activities | May remove overlap days | Rework and coordination | Deliverables can be developed with controlled uncertainty |
| Stop compressing | Preserves the current plan | May miss the target date | The next gain is too expensive or risky |
Recalculate after every change
Do not select all cheap activities once and assume they will remain useful. After each crash or overlap:
- Update the activity duration or dependency.
- Recalculate early and late dates.
- Find the new critical path or paths.
- Check float on near-critical paths.
- Record cost, risk, and quality effects.
- Stop if the next change gives no acceptable benefit.
Only a change that shortens the current project duration provides schedule gain. A cheap activity with float may improve its own finish date without changing the project finish date.
Combining crashing and fast-tracking
The techniques can be combined, but their gains are not automatically additive. Suppose crashing saves two days and fast-tracking appears to save three more. The project may save fewer than five days because both changes affect the same controlling path, or because one change makes the other less effective.
A practical sequence is:
- Establish the approved baseline schedule and target date.
- Identify the current critical path and near-critical paths.
- Test low-risk fast-tracking opportunities.
- Recalculate the network and inspect new dependencies.
- Crash critical activities when the remaining gap justifies the added cost.
- Recalculate after each change.
- Compare the final date with total cost, rework exposure, and resource demand.
You can also crash first and then fast-track. The better order depends on the project. Fast-tracking may be preferable when direct budget is limited. Crashing may be safer when rework would be expensive or quality-sensitive.
When to stop
Stop compressing when the target date is reached or when the next change has no feasible schedule gain. Also stop when the added cost, safety exposure, quality risk, or coordination load exceeds the value of finishing earlier.
If the required date remains impossible, discuss a different constraint. Options may include changing scope, adding external capacity, moving the deadline, or accepting a phased delivery. Compression is a planning trade-off, not a substitute for a feasible project plan.
# Compare a proposed compression with its value.
normal_days = 14
compressed_days = 11
crash_cost = 900
rework_reserve = 300
value_per_day_early = 250
days_saved = normal_days - compressed_days
net_value = days_saved * value_per_day_early - crash_cost - rework_reserve
print(f"Days saved: {days_saved}")
print(f"Expected net value: {net_value}")
print("Proceed" if net_value > 0 else "Do not proceed")Exercise
A crashing change saves one day but costs 600. A fast-tracking change appears to save two days but has an expected rework cost of 500. The value of finishing one day early is 400. Should you approve both changes based only on these figures?
Show answer
No. Their gains may overlap, and the fast-tracking risk may affect quality or the critical path. Recalculate the network after each change, then compare the actual days saved with the 600 crash cost and the 500 expected rework cost.