When Resources Break the Critical Path
The assumption behind the critical path
This chapter assumes you understand tasks, durations, dependencies, and the basic critical path calculation. The standard critical path method (CPM) assumes that every task can use its required people, equipment, and materials when needed. In practice, that assumption often fails.
A resource constraint is a limit on the availability of something needed to perform work. A developer, crane, testing lab, or specialist may be available to only one task at a time. Two tasks can have no logical dependency but still compete for the same resource.
The logical critical path comes from dependency links and durations. A resource-constrained schedule adds another kind of dependency: a task must wait because its resource is busy.
A simple example
Suppose tasks A and B both require the same specialist:
| Task | Duration | Logical predecessors | Required specialist |
|---|---|---|---|
| A | 4 days | None | 1 |
| B | 3 days | None | 1 |
| C | 2 days | A and B | 1 |
With unlimited specialists, A and B can run together. C starts after both finish, so the project takes 6 days.
If only one specialist is available, A and B cannot overlap. The scheduler must choose an order:
- A, then B, then C: 4 + 3 + 2 = 9 days.
- B, then A, then C: 3 + 4 + 2 = 9 days.
The resource limit has created an effective dependency between A and B. The original network did not show this link, so the original critical path calculation understated the project duration.
Resource leveling and critical chain
Resource leveling changes task dates to prevent over-allocation. Over-allocation means that a resource is scheduled for more work than it can perform at one time. Leveling may delay tasks, split them, or change their order. The project finish date can move later.
The critical chain is the longest resource- and dependency-constrained sequence in a schedule. It extends critical path thinking by considering resource availability. A task that had float in the original network can become critical after leveling if a resource delay consumes that float.
Resource leveling and resource smoothing have different purposes:
| Technique | Main goal | Can change the finish date? |
|---|---|---|
| Resource leveling | Remove resource over-allocation | Yes |
| Resource smoothing | Fit work within available float | Usually no |
A practical workflow is:
- Calculate the logical critical path.
- Identify resources assigned to each task.
- Find periods where the same resource is assigned to overlapping work.
- Level the schedule and recalculate dates and float.
- Monitor the new critical chain and near-critical tasks.
Decisions and risks
When resources conflict, compare the cost of delaying work with the cost of adding capacity. You might assign another specialist, outsource a task, change the sequence, or reduce task scope. Do not simply move a noncritical task without recalculating. Its available float may be smaller than expected, and another path may become critical.
> callout warning > A resource-constrained schedule can have a different critical path every time task priorities or resource assignments change. Recalculate after meaningful changes.
Exercise
Tasks A and B can run in parallel logically, but both need the only available tester. A takes 5 days, B takes 2 days, and C takes 1 day after both. What is the shortest finish time if the tester can work on only one task at a time?
Show answer
The shortest finish time is 8 days: 5 days for A, 2 days for B, and 1 day for C.