Sub topic 4
Checking the Network Before You Calculate
Assume you know basic project terms such as task, duration, milestone, and dependency. You can read a task list or simple Gantt chart and perform basic arithmetic with durations. This chapter focuses on validating the activity network before calculating the critical path.
A critical path calculation assumes that the network correctly represents the project. A network is a set of activities connected by dependency links. Each activity has a duration and may have predecessors, which are activities that must finish before it can start.
An incorrect link can produce a convincing but false project duration. Validate the structure first.
What a valid network contains
A well-formed network normally has:
- One intended start point, or a clearly defined set of activities that can start at time zero.
- One intended finish point, or a final milestone that gathers all completed work.
- A duration for every activity.
- A unique identifier for every activity.
- A predecessor relationship for each activity that depends on earlier work.
- No dependency cycle.
- A route from every planned activity to the project finish.
The network does not need to contain only one start and finish activity. However, adding explicit start and finish milestones often makes errors easier to detect.
Check for cycles
A cycle occurs when dependencies loop back to an earlier activity. For example:
- Design must finish before Build.
- Build must finish before Test.
- Test must finish before Design.
This loop has no valid starting point. A forward pass cannot calculate an earliest start because each activity waits for another activity in the same loop.
Cycles often result from entering a dependency in the wrong direction. Ask, “Which activity must finish first?” Then draw the arrow from that activity to the activity that follows it.
Check for missing or incorrect links
A missing predecessor makes work appear available too early. For example, if testing requires a completed build but Test has no link from Build, the calculation can schedule testing at the project start.
An incorrect link can delay work unnecessarily. If Documentation depends on Final Approval when it only needs the first approved draft, the network may show a longer project than the real process requires.
Also check for:
- Activity names that appear twice with different meanings.
- Tasks with no duration or an accidental zero duration.
- A task that has predecessors but cannot be reached from the start.
- A task that has no successor even though more work follows it.
- A final milestone that does not depend on every required completion branch.
| Validation check | Possible symptom | Correction |
|---|---|---|
| Every required task has predecessors | Work starts too early | Add the missing dependency |
| Every task reaches the finish | Work is omitted from the project duration | Connect the task to its successor |
| No dependency cycles | The calculation cannot progress | Reverse or remove the incorrect link |
| One clear finish milestone | Some branches end independently | Connect all final branches |
A practical validation sequence
- List every activity and give it a unique identifier.
- Mark the intended start and finish points.
- For each activity, ask what must finish before it starts.
- For each activity, ask what work it enables.
- Trace each route from the start to the finish.
- Look for a route that returns to an earlier activity.
- Confirm that every required task appears on at least one route.
- Only then run the forward and backward passes.
For a larger network, topological ordering provides a useful test. A topological order lists each activity after all its predecessors. If you cannot produce such an order, the network contains a cycle or an unresolved link.
Exercise
A schedule contains Start → Design → Build → Finish. Testing is required after Build, but Testing has no successor. What should you check?
Show answer
Check whether Testing should connect to Finish or to another required activity. If Testing is required for project completion, leaving it disconnected would exclude its duration from the calculated project finish.