Sub topic 9
Multiple Critical Paths and Near-Critical Paths
Assume you already know how to build a dependency network and calculate total float with forward and backward passes. This chapter uses durations in working days and assumes the network has no cycles.
A critical path is a chain of dependent activities whose total duration determines the shortest possible project duration. Activities on a critical path have zero total float. A project can have more than one critical path when two or more paths have the same longest duration.
How multiple critical paths arise
Consider this network:
flowchart TD
A["A: 2 days"] --> B["B: 4 days"]
A --> C["C: 4 days"]
B --> D["D: 2 days"]
C --> D
C --> E["E: 1 day"]
D --> F["Finish"]
E --> Fcaption: Two equal critical paths with a near-critical branch alt: Activity A splits into B and C. Both lead to D, while C also leads to E. D and E lead to Finish.
The path lengths are:
| Path | Calculation | Length | Status |
|---|---|---|---|
| A-B-D | 2 + 4 + 2 | 8 days | Critical |
| A-C-D | 2 + 4 + 2 | 8 days | Critical |
| A-C-E | 2 + 4 + 1 | 7 days | Near-critical |
The project cannot finish before day 8. Both A-B-D and A-C-D therefore have zero total float. A delay to either path can delay the project.
Notice that critical paths can share activities. Activity A and activity D belong to both critical paths. A delay to either shared activity affects both paths at once. This creates more risk than simply counting the paths suggests.
Near-critical paths
A near-critical path is a path whose duration is close to the longest path but has some positive float. There is no universal cutoff. A team might define a near-critical path as one with one or two days of float, or with less than 10% of the total project duration.
Near-critical paths matter because their float can disappear during execution. For example, the A-C-E path above is one day shorter than the project duration. If E takes two extra days, that path becomes critical. If C takes one extra day, both A-C-D and A-C-E become longer, and the schedule risk increases.
Track near-critical paths when they contain uncertain work, external approvals, scarce resources, or activities with a history of delay.
Practical risk analysis
For each reporting period:
- Recalculate the forward and backward passes using actual progress and remaining durations.
- List every zero-float path, not only the first path found by scheduling software.
- Record near-critical paths and their current float.
- Check shared activities because they can affect several paths.
- Review whether a delay on a near-critical path could consume its float before the next milestone.
The critical path is a current result of the schedule model, not a permanent property of the project. When durations, logic, or constraints change, the critical and near-critical paths can change too.
Exercise
A project has two longest paths, each lasting 12 days. One path shares three activities with the other. What should the project manager do?
Show answer
Treat both paths as critical, monitor the shared activities especially closely, and recalculate the paths whenever actual progress or remaining durations change.