Total Float and Free Float
This chapter assumes you can read an activity network and understand the forward and backward passes. You should also know each activity’s earliest start (ES), earliest finish (EF), latest start (LS), and latest finish (LF).
Float is the amount of scheduling flexibility an activity has. It helps you distinguish activities that can move from activities that will delay the project or a successor.
Total float
Total float is the time an activity can be delayed without delaying the planned project completion date.
Calculate it in either of these equivalent ways:
Total float = LS - ESTotal float = LF - EF
For example, if an activity has ES 3, EF 5, LS 5, and LF 7, its total float is 2 days. It may start as late as day 5 instead of day 3 and still finish the project on time.
Activities with zero total float are critical under the assumptions in the schedule. A delay to one of them can delay the project finish.
Free float
Free float is the time an activity can be delayed without delaying the earliest start of any immediate successor.
For an activity with successors, calculate it as:
Free float = earliest successor start - activity earliest finish
Use the smallest successor start when an activity has several successors. For a final activity, free float is usually calculated against the planned project finish.
Free float cannot be greater than total float. An activity may have total float but no free float if delaying it would immediately delay a successor, even though the project has some later flexibility.
Worked example
Consider this network:
The forward pass gives A an EF of 3, B an EF of 5, C an EF of 7, and D an EF of 10. The backward pass gives B two days of total float. The other activities have zero total float.
| Activity | ES | EF | LS | LF | Total float | Free float |
|---|---|---|---|---|---|---|
| A | 0 | 3 | 0 | 3 | 0 | 0 |
| B | 3 | 5 | 5 | 7 | 2 | 2 |
| C | 3 | 7 | 3 | 7 | 0 | 0 |
| D | 7 | 10 | 7 | 10 | 0 | 0 |
Activity B can start two days late without delaying D’s earliest start. Therefore, its total and free float are both two days.
Activity A has no free float because both B and C start at day 3. Delaying A would delay both successors. Activity C is critical because it has zero total float.
Common errors
- Treating float as extra time that can always be spent. A team may already need it for risk, approvals, or resource conflicts.
- Calculating free float from the latest successor start. Free float uses the earliest successor start.
- Assuming one zero-float path remains critical forever. New estimates, actual delays, and changed dependencies can create another critical path.
- Ignoring calendars. Weekends, holidays, and working-hour rules must use the same time basis throughout the calculation.
A practical schedule report should show both floats. Total float supports project-level decisions. Free float shows where a delay will first affect another activity.
activities = {
"A": {"ef": 3, "successor_es": [3]},
"B": {"ef": 5, "successor_es": [7]},
"C": {"ef": 7, "successor_es": [7]},
"D": {"ef": 10, "successor_es": []},
}
latest_finish = {"A": 3, "B": 7, "C": 7, "D": 10}
earliest_start = {"A": 0, "B": 3, "C": 3, "D": 7}
for name, activity in activities.items():
total_float = latest_finish[name] - activity["ef"] - (
latest_finish[name] - earliest_start[name]
)
# Equivalent to LS - ES when LS = LF - duration.
# Here we use the simpler displayed values below.
free_float = min(activity["successor_es"], default=[10])[0] - activity["ef"]
print(name, "free float:", free_float)The code illustrates the free-float calculation, but a complete scheduling implementation should store duration, ES, EF, LS, and LF explicitly.
Exercise
Activity X has ES 4, EF 9, LS 6, and LF 11. Its immediate successors have earliest starts of 12 and 14. What are its total float and free float?
Show answer
Total float is 2 days because LS - ES = 6 - 4. Free float is 3 days because the earliest successor start is 12 and 12 - 9 = 3.