Keeping the Critical Path Current During Execution
Assume you can read a task network, understand predecessor links, and calculate durations in days. You should also know the meaning of a baseline, which is the approved schedule used for comparison. This chapter focuses on updating the network after work starts.
The critical path is a result of the current schedule data. It is not a permanent label assigned at project kickoff. As actual work replaces estimates, the longest path can change. A task that was noncritical can become critical when it takes longer than expected. A delayed task can also add time to a different path and create a new project completion date.
Use a status date
Choose a status date, which is the point in time at which you stop recording actual progress. For every activity, record:
- Actual start and finish dates, if the work has happened.
- Remaining duration for unfinished work.
- Actual logic, including newly discovered predecessor links.
- Approved scope or dependency changes.
- Resource or calendar changes that affect the forecast.
Do not simply reduce the original duration by the percentage complete. Remaining work can take longer or shorter than the original estimate.
| Activity | Baseline duration | Actual or remaining information | Current forecast |
|---|---|---|---|
| Design | 3 days | Finished in 4 days | 4 days actual |
| Build | 5 days | Started; 3 days remain | 7 days total |
| Test | 2 days | Not started | 2 days |
After updating the data, run the forward and backward calculations again. Use actual finish times for completed work and remaining durations for unfinished work. The resulting longest path is the current critical path, and its finish is the current forecast completion date.
Compare forecast with the baseline
Keep the baseline unchanged unless your governance process formally approves a rebaseline. Compare the current forecast against it to show schedule variance.
For example, suppose the original critical path was A–C–D and required 10 days. During execution, C takes two extra days. If the other path has available float, the project forecast may move to 12 days while the critical path remains A–C–D. If another path had only one day of float, it may also become critical after the change.
Review these items at each reporting cycle:
- Current forecast finish versus baseline finish.
- Tasks with zero total float.
- Near-critical tasks with little remaining float.
- Changes to predecessors, successors, calendars, or scope.
- Whether the corrective action changes the network or only the estimate.
Act on changes, then recalculate
A mitigation plan is part of the schedule only after its assumptions are represented. If you add staff, update the duration and resource availability. If you overlap design and testing, change the dependency type and record the risk. If you approve additional scope, add the activities and links.
A schedule can have several critical paths. Therefore, reducing one path may not reduce the project duration if another path finishes at the same time. Check all zero-float and near-critical paths after every major update.
Exercise
A project has two paths. Path A finishes on day 20 and Path B finishes on day 18. A two-day delay affects Path B. What should you do before claiming that the project is delayed?
Show answer
Update the remaining schedule and recalculate both paths. Path B may now finish on day 20, creating two critical paths without changing the project finish. Further delay on either path would then delay the project.