Sub topic 8
Reading the Critical Path from Zero Float
Prerequisites and working model
This chapter assumes you can read a task network, identify predecessor links, and calculate earliest and latest start and finish times. The critical path is the longest connected chain of activities in a project network. Its length sets the shortest possible project duration when the schedule has no delays.
Total float is the amount of time an activity can slip without delaying the project finish date. An activity has zero total float when:
latest start - earliest start = 0
The usual calculation is:
total float = latest start (LS) - earliest start (ES)
You can also calculate it as:
total float = latest finish (LF) - earliest finish (EF)
The two results should match.
Worked example
Consider this network:
The forward pass gives each activity its earliest possible times. The backward pass gives its latest allowable times, working back from the project finish.
| Activity | Duration | ES | EF | LS | LF | Total float |
|---|---|---|---|---|---|---|
| A | 3 | 0 | 3 | 0 | 3 | 0 |
| B | 2 | 3 | 5 | 5 | 7 | 2 |
| C | 4 | 3 | 7 | 3 | 7 | 0 |
| D | 3 | 7 | 10 | 7 | 10 | 0 |
The project takes at least 10 days. Activities A, C, and D have zero total float, so they form the critical path:
A → C → D
Activity B is not critical. It can start as late as day 5 instead of day 3, giving it two days of total float. If B starts two days late, D can still start on day 7 because C is the predecessor that finishes later.
What zero float tells you
Zero float identifies activities that currently control the planned finish date. A delay to any activity on the critical path usually delays the whole project by the same amount, unless you change the network, duration, resources, or working calendar.
Zero float does not mean that an activity is more important in every sense. A noncritical activity may still have high cost, safety importance, or a hard deadline. Float only describes its timing flexibility within this schedule.
Free float is narrower than total float. It is the time an activity can slip without delaying the earliest start of any immediate successor:
free float = earliest successor start - earliest finish
In the example, B has two days of free float because D cannot start before day 7. An activity can have total float but less free float when its delay consumes time that a successor could otherwise use.
Multiple critical paths
Two or more paths can have the same longest duration. In that case, each path is critical. The project has greater schedule risk because a delay on any tied path can delay completion.
A near-critical path has a small amount of float. It may become critical after a minor delay. Monitor these activities alongside the zero-float activities, especially when estimates are uncertain.
Exercise
In the example, activity B is delayed from day 3 to day 5. Does the project finish later?
Show answer
No. B has two days of total float, so it finishes on day 7 at the latest. Activity C still controls the start of D, and the project finishes on day 10.