Shortening the Schedule: Crashing and Fast-Tracking
Assume you can read a dependency network and calculate the critical path, earliest dates, and float. This chapter uses those results to shorten a schedule. The key rule is that shortening a noncritical activity does not shorten the project unless it changes a path that determines the project finish.
Two ways to shorten a schedule
Crashing means adding resources or spending more money to reduce an activity's duration. Examples include assigning another engineer, paying for overtime, renting faster equipment, or outsourcing part of the work. Crashing usually increases cost, but it does not normally change the dependency logic.
Fast-tracking means overlapping activities that were originally planned in sequence. For example, a team might begin construction from approved design sections while the remaining design work continues. Fast-tracking can shorten the calendar without adding many resources, but it increases coordination, rework, and quality risks.
| Method | Main change | Typical benefit | Main risk |
|---|---|---|---|
| Crashing | More cost or resources | More predictable duration reduction | Higher cost or resource conflicts |
| Fast-tracking | More overlap | Shorter calendar time | Rework and coordination errors |
Start with the critical path
Consider this network:
- A takes 3 days.
- B takes 2 days after A.
- C takes 4 days after A.
- D takes 3 days after both B and C.
The two paths are A-B-D, which takes 8 days, and A-C-D, which takes 10 days. The critical path is A-C-D, so the project duration is 10 days.
Crashing B first does not help. B is on the shorter path and has 2 days of float. Crashing C or D can help because both are on the critical path.
Apply crashing carefully
Suppose C can be reduced from 4 days to 3 days by adding a specialist. The critical path becomes 9 days. Before approving the change, compare:
- The extra cost per day saved.
- Whether the required resource is available.
- Whether the shorter estimate is realistic.
- Whether the change creates quality or safety problems.
- Whether another path becomes critical.
If C is reduced by 2 days, the A-C-D path becomes 8 days. It then ties with A-B-D. The schedule now has two critical paths. A later delay on either path can delay the project, so the apparent gain also increases schedule risk.
A shared activity such as A or D may be a better crashing target when several critical paths exist. Shortening a shared activity can reduce every path that passes through it. You must still check whether the activity can actually be shortened and whether its cost is acceptable.
Apply fast-tracking carefully
Fast-tracking works only when the successor can begin with incomplete predecessor work. It may be safe when work can be divided into stable parts. It is dangerous when the successor depends on the predecessor's final result.
For example, D might start after C delivers its first approved section instead of waiting for all of C. If this saves one day, the project may finish in 9 days. However, changes to C's unfinished sections could force D to redo work. Record the overlap as a deliberate schedule assumption, assign an owner, and define what happens when the assumption fails.
A practical decision sequence
- Confirm the current critical and near-critical paths.
- List activities that can be crashed or safely overlapped.
- Compare cost, achievable savings, risk, and resource effects.
- Make the smallest useful change.
- Recalculate dates and float.
- Monitor the new assumptions during execution.
Exercise
The critical path is A-C-D and lasts 10 days. Activity B is on an 8-day path. Which activity should you examine first if you want to crash the schedule, and why?
Show answer
Examine C or D first. They are on the critical path, while B has float and shortening it alone will not reduce the 10-day project duration.