Sub topic 10
Dependency Types, Leads, and Lags
Assume you know how activities, durations, predecessors, and the critical path work. This chapter extends that model beyond the simplest rule: “task B starts when task A finishes.” A dependency type describes how two activities relate. A lead or lag adds a time offset to that relationship.
The four dependency types
Project schedules commonly use these relationships:
| Type | Meaning | Example |
|---|---|---|
| Finish-to-start (FS) | The successor starts after the predecessor finishes | Build starts after design finishes |
| Start-to-start (SS) | The successor starts after the predecessor starts | Testing starts after development starts |
| Finish-to-finish (FF) | The successor finishes after the predecessor finishes | Documentation finishes after development finishes |
| Start-to-finish (SF) | The successor finishes after the predecessor starts | A new support shift starts before the old shift finishes |
Finish-to-start is the usual default. The other types can represent real overlap, handoffs, and transitions. Do not use them merely to make a schedule fit a preferred date.
Leads and lags
A lag is a waiting period inserted between related events. For example, “Build starts two days after design finishes” is an FS dependency with a two-day lag. The successor cannot start until the predecessor finishes plus two days.
A lead allows the successor to overlap the predecessor. It is usually written as a negative lag. For example, “Testing starts one day before development finishes” is an FS dependency with a one-day lead, or FS -1 day.
The basic constraint for an activity relationship is:
successor event time >= predecessor event time + lag
The events depend on the relationship type. For an FS link, the predecessor finish controls the successor start. For an SS link, the predecessor start controls the successor start. The same idea applies to FF and SF.
Positive lags often represent curing, shipping, review, or approval time. Leads can represent phased work, but they require evidence that the successor can begin safely before the predecessor ends.
Effects on the critical path
Dependency types and offsets change the arithmetic in both passes. In a forward pass, calculate the earliest time permitted by every predecessor relationship, then take the latest permitted value. In a backward pass, apply the same relationship in reverse to determine the latest allowable event times.
A lead can shorten the calculated project duration by allowing overlap. A lag can lengthen it. Either one can move the critical path to a different chain. A path that was noncritical under plain FS links may become critical after a lag is added.
Check these points when reviewing a linked schedule:
- Confirm that the relationship matches the real handoff.
- Record the reason and owner for every lag.
- Test whether a lead creates an unsafe or impossible overlap.
- Recalculate float after changing a link.
- Look for excessive use of constraints or date overrides that hide dependencies.
Exercise
Development lasts 10 days. Testing has an FS dependency with a two-day lag after development. If development starts on day 0, when can testing start?
Show answer
Development finishes on day 10. Testing can start on day 12, because the two-day lag is added after the predecessor finish.