Modelling a Project as an Activity Network
A critical path analysis starts with a model of the project. An activity network represents work as activities connected by dependency links. An activity is a piece of work with a duration, such as “design the database” or “install the equipment.” A dependency link states that one activity must wait for another activity, or for a specific event, before it can start.
The network shows the project’s logical order. It does not show calendar dates, team assignments, or costs by itself. Those details can be added later, but the dependency logic must be correct first.
Prerequisites
This chapter assumes that you understand task, duration, milestone, and dependency. You should also be able to read a simple task list or Gantt chart and add durations in days. The later calculations use basic Python, but programming is optional for understanding the model.
Activities, nodes, and links
In an activity-on-node network, each activity is shown as a node. The node usually contains an identifier, a description, and a duration. Arrows point from predecessor activities to successor activities.
A predecessor is an activity that must happen first. A successor is an activity that depends on it. For example, testing may depend on implementation:
- Implementation is the predecessor.
- Testing is the successor.
- The arrow from implementation to testing represents the dependency.
Consider this small project:
| Activity | Description | Duration | Predecessors |
|---|---|---|---|
| A | Gather requirements | 3 days | None |
| B | Design solution | 2 days | A |
| C | Build solution | 4 days | B |
| D | Prepare training | 2 days | A |
| E | Launch project | 1 day | C, D |
Activities B and D can begin after A finishes. Activity E must wait for both C and D. This branching and joining structure is what makes a network more informative than a simple task list.
Model the work, not just the headings
Each activity should represent a meaningful unit of work whose start and finish can be identified. Avoid making one activity contain several unrelated tasks. If “build and test” must be separated because testing can begin only after building is complete, model them as two activities.
Use milestones for zero-duration events, such as “contract approved” or “release accepted.” A milestone marks a condition or decision. It is not a task that consumes working time.
Write predecessor links as clearly as possible. “B depends on A” means that B cannot start until the stated completion condition for A is met. Do not add links merely because activities appear in a particular order on a list. Unnecessary links can make the schedule longer and hide useful parallel work.
A useful network normally has one starting point and one ending point, even if the project contains several independent workstreams. You can add a zero-duration start milestone and finish milestone to connect those workstreams. Every activity should be reachable from the start and should lead, directly or indirectly, to the finish.
Exercise
Exercise
In the example network, which activities can start after A finishes, and which activities must finish before E can start?
Show answer
B and D can start after A finishes. C and D must both finish before E can start.