Sub topic 2
Activity durations and what they assume
This chapter assumes you know basic project terms such as task, duration, milestone, and dependency. You should also be comfortable adding durations in days. Python knowledge is optional.
A critical path calculation is only as useful as its activity durations. A duration is the amount of working time an activity is expected to require. It is an estimate, not a promise. If the estimates are too short, the calculated project finish date will also be too early.
Work time is not always elapsed time
First decide what a duration measures. A task estimated at three days might mean:
- Three working days for one person.
- Three calendar days, including weekends.
- Three days of elapsed time while other work happens in parallel.
- Three days after a dependency is satisfied.
These meanings produce different schedules. Record the unit and calendar used by the project. For example, “three working days using the standard Monday-to-Friday calendar” is more precise than “three days.”
Also separate effort from duration. Effort is the amount of labor required. Duration is the time between starting and finishing. One person working for four days might represent four person-days of effort. Two people might complete the same work in two days, but only if the work can be divided and coordination does not add more time.
What a single estimate assumes
A fixed duration usually assumes that:
- The activity has a defined scope.
- The assigned resources are available when needed.
- Required inputs, tools, and approvals arrive on time.
- The work follows the stated quality standard.
- The project calendar and working hours are known.
- No unexpected rework occurs.
Write these assumptions down. They explain why an estimate might change later. For example, “implement payment validation: five working days” may assume that the payment provider’s interface is already available and that the design is approved.
A dependency can also affect the practical duration. A task may require two days of work but take five elapsed days because it waits for a review between its work steps. Model the waiting time separately as a lag when the scheduling method supports it, or include it explicitly in the activity description.
Using ranges instead of false precision
Early in a project, uncertainty is often larger than the difference between nearby estimates. A range such as three to six working days can communicate this better than “four days.” You can later choose a planning value, such as the most likely duration, and update it as evidence improves.
Three-point estimation records three values:
- Optimistic: the shortest reasonable duration.
- Most likely: the duration expected under normal conditions.
- Pessimistic: a reasonable longer duration that includes known risks.
PERT, or Program Evaluation and Review Technique, combines these values with a weighted average. It gives four times as much weight to the most likely estimate as to each extreme.
def pert_expected(optimistic, most_likely, pessimistic):
if not (optimistic <= most_likely <= pessimistic):
raise ValueError("Estimates must be optimistic <= most likely <= pessimistic")
return (optimistic + 4 * most_likely + pessimistic) / 6
expected_days = pert_expected(2, 4, 12)
print(f"{expected_days:.1f} working days")This prints 5.0 working days. The result is still an estimate. It does not guarantee that the activity will finish in five days.
Choosing a duration for critical path analysis
Use durations that match the decision you need to make. For a committed delivery date, include normal interruptions, reviews, and expected rework. Do not hide a known waiting period inside a number if stakeholders need to see its cause.
Keep the source of each estimate visible. Historical data is usually stronger than an unsupported guess. When no history exists, ask the person doing the work to provide the three-point values and explain the assumptions.
Exercise
An activity has optimistic, most likely, and pessimistic estimates of 3, 5, and 9 working days. What is its PERT expected duration, and what assumption should you document before using it in a schedule?
Show answer
The expected duration is (3 + 4 × 5 + 9) / 6 = 5.3 working days. Document the calendar, available resources, scope, and conditions behind the three estimates.