Sub topic 4
Writing a Project Charter
This chapter assumes you know the DMAIC phases, the idea of a tollgate review, and the roles of Champion, Black Belt, Green Belt and Process Owner. It covers the charter, the main deliverable of the Define phase. You will learn what goes into it, how to write each element so it can be tested, and which errors cause trouble at the first tollgate.
What a charter is for
A project charter is a short document that records what the project will do, why it matters, who is involved and what limits apply. The Champion and the team agree on it before real work starts. Its uses are:
- It gives the Champion something to approve, so sponsorship is explicit.
- It sets the scope, so the team can refuse unrelated requests.
- It is the reference for every later tollgate. Reviewers compare the evidence with what the charter promised.
The charter is a living document. The Measure phase may show that the baseline differs from what the team assumed, so the goal may be revised. Any change should be agreed with the Champion and recorded, not made quietly.
The elements of a charter
| Element | Question it answers | Typical content |
|---|---|---|
| Business case | Why does this matter now? | Cost, risk or customer impact, linked to a business priority |
| Problem statement | What is wrong, where and how big? | Measured gap, time frame, location |
| Goal statement | What will change, by how much, by when? | Metric, target, deadline |
| Scope | What is in and out? | Process start and end points, exclusions |
| Constraints and assumptions | What limits the team? | Budget, systems, regulations, staffing |
| Team and roles | Who does what? | Champion, Process Owner, Black Belt or Green Belt, members |
| Milestones | When is each tollgate? | Dates for the five phases |
| Risks | What could derail the project? | Known risks with owners |
Writing the problem statement
A good problem statement describes the symptom with data. It does not name a cause or a solution. It should answer four things: what is measured, how far it is from the expectation, over what period, and in which process.
Compare two versions.
- Weak: "Our invoicing process is slow and the new software is needed."
- Better: "Between January and June, 31% of customer invoices (1,240 of 4,000) were issued more than five business days after shipment, against a customer requirement of two days. This delayed cash collection by an average of eight days."
The weak version states a solution ("new software") before any analysis. It also gives no numbers. The better version is specific enough that the team can check it in the Measure phase.
If you cannot write the problem with numbers, you may still be in an early stage. In that case, say the baseline is unknown and make "establish the baseline" a Measure deliverable. Do not invent figures to fill the field.
Writing the goal statement
Use the SMART pattern: specific, measurable, achievable, relevant and time-bound. A useful goal names the same metric as the problem statement, so the two can be compared directly.
- Metric: the same one used in the problem statement.
- Baseline: the current value.
- Target: the value to reach.
- Deadline: a date.
Example: "Reduce invoices issued later than two business days after shipment from 31% to 10% or less by 30 September."
Two checks help here. First, the target should come from a customer need or a business case, not from a round number. Second, the goal should be achievable but not already solved. If the target needs only a small tweak, the project may not need DMAIC.
Primary and secondary metrics
Most charters name one primary metric, often called the Y. Add secondary metrics to guard against shifting the problem elsewhere. If you cut invoicing time by skipping checks, error rates may rise. A consequential metric such as invoice error rate should be tracked so that any rise is visible.
Defining scope
Scope says where the process under study starts and ends. It is usually written as a start event and an end event, such as "starts when the shipment is confirmed and ends when the invoice is sent". Add an "out of scope" list, for example "credit approval" and "payment collection".
Scope that is too wide is the most common charter error. The project then runs for a year and loses its sponsor. Scope that is too narrow can leave the real cause outside the boundaries. A practical test is that the team should be able to finish in roughly three to six months, and the team should have some authority over the process it is studying. The SIPOC map, covered in a later chapter, helps confirm the boundaries.
Team, roles and milestones
Name people, not departments. At minimum record:
- The Champion, who approves the charter and removes obstacles.
- The Process Owner, who runs the process day to day and will receive the handover.
- The Black Belt or Green Belt, who leads the work.
- Team members who know the process, with the share of time each can give.
Include the Process Owner from the start. A project that reaches Control without an owner who agreed to the changes tends to fail at handover.
Milestones should list a planned date for each of the five tollgates. Dates are estimates and may move, but they show whether the plan is realistic.
A charter as structured data
Some teams keep charters in a tracking tool. The code below checks a draft charter for missing fields and for a problem statement that includes a number. The number check is crude, but it catches the common error of a statement with no measured gap.
import re
REQUIRED = [
"business_case",
"problem_statement",
"goal_statement",
"scope_in",
"scope_out",
"champion",
"process_owner",
"project_lead",
"milestones",
]
def check_charter(charter):
issues = []
for field in REQUIRED:
if not charter.get(field):
issues.append(f"Missing: {field}")
problem = charter.get("problem_statement", "")
if problem and not re.search(r"\d", problem):
issues.append("Problem statement contains no number")
return issues
draft = {
"business_case": "Late invoices delay cash collection",
"problem_statement": "Invoices are often late",
"goal_statement": "Reduce late invoices from 31% to 10% by 30 September",
"scope_in": "Shipment confirmation to invoice sent",
"scope_out": "Credit approval, payment collection",
"champion": "Finance Director",
"process_owner": "",
"project_lead": "A. Rivera",
"milestones": {"Define": "2026-12-15"},
}
for issue in check_charter(draft):
print(issue)Running it prints Missing: process_owner and Problem statement contains no number.
Common errors
- Solution in the problem statement. Writing "we need a new system" closes off analysis. State the gap and let the Analyze phase find the cause.
- No baseline. A goal such as "improve satisfaction" has no starting value, so success cannot be shown.
- Scope drift. New requests are added informally. Route them through the Champion and record the change.
- Absent Process Owner. The people who must sustain the gains were never consulted.
- Unlinked business case. If the savings or risk cannot be tied to a number the finance team accepts, sponsors lose interest.
How the charter connects to the tollgate
At the Define tollgate, reviewers usually check that the charter is signed, that the problem and goal use the same metric, that the scope is bounded and that the team and Process Owner are named. Voice of the customer and SIPOC work, covered in the next chapters, supply the supporting evidence.
Exercise
A draft charter says: "Customer complaints are too high, so we will implement a new complaints portal and cut complaints in half." Name two faults in this charter and rewrite the problem statement, using made-up but plausible numbers.
Show answer
Faults: the problem statement has no measured gap, period or location, and it names a solution (a portal) before analysis. The goal also lacks a baseline and a deadline. A rewrite: "From July to September, the billing support team received 420 complaints per 10,000 orders, against a target of 150 per 10,000 orders. Complaints about billing errors made up 60% of the total." The goal can then be: "Reduce billing complaints from 420 to 150 per 10,000 orders by 31 March."
Exercise
Why should a charter list secondary metrics, and what would be a reasonable secondary metric for a project that shortens call handling time?
Show answer
Secondary metrics show whether improving the primary metric makes something else worse. For a project that shortens call handling time, a reasonable secondary metric is the first-contact resolution rate or customer satisfaction score, because agents could rush calls and leave problems unsolved.