Scoping the process with SIPOC
This chapter assumes you know the DMAIC phases at a high level and have seen a project charter. It covers how a SIPOC diagram fixes the boundaries of the process under study during Define, and how to build one that survives a tollgate review.
What SIPOC is
SIPOC is a one-page, high-level map of a process. The letters stand for:
- Suppliers: who or what provides the inputs.
- Inputs: the materials, information and resources the process consumes.
- Process: four to seven high-level steps that transform inputs into outputs.
- Outputs: what the process produces, including services, documents and data.
- Customers: who receives the outputs.
SIPOC is read left to right, but teams often build it right to left. Starting from customers and outputs keeps the map tied to the voice of the customer and the CTQ requirements from the previous chapter.
Why Define needs it
A charter names a problem and a goal, but the problem statement rarely says where the process starts and stops. Without that, the team collects data from the wrong places, the sponsor and team picture different processes, and the project grows over time (scope creep). SIPOC settles three questions early:
- Boundaries. Which step is the first one in scope and which is the last?
- Stakeholders. Which suppliers and customers must be consulted, informed or kept out of the project?
- Measurement points. Where can you measure the Y (the output metric from the charter) and the candidate Xs (the inputs and steps that might drive it)?
The map is also the input to later work. The Measure phase uses its steps to decide where to sample. The Analyze phase starts from the same steps when it builds detailed process maps.
Building a SIPOC step by step
- Name the process and its goal. Copy the Y from the charter, for example "invoice cycle time from receipt to payment".
- List the process steps. Use verb-noun phrases ("Match invoice to purchase order"). Aim for four to seven steps. Fewer than four usually hides the problem. More than seven means you are drawing a detailed flowchart, which belongs in Analyze.
- Fix the boundaries. Write the trigger of the first step ("Invoice received") and the end of the last step ("Payment released"). Anything before or after is out of scope, even if the team suspects the cause lies there. Record the suspicion for the sponsor instead of quietly expanding.
- List outputs. Include every output a customer receives, not only the main one. Mark which outputs relate to the CTQs.
- List customers. Include internal customers, such as the next department, and external ones.
- List inputs and suppliers. For each input, name the supplier. Include information inputs, such as a purchase order number, since missing information is a common source of defects.
- Review with the people who do the work. A SIPOC drawn in a meeting room often describes the process as designed, not as performed. Walk it with operators before the tollgate.
A worked example
A finance team has a charter goal of cutting supplier invoice cycle time. Their SIPOC:
| Suppliers | Inputs | Process | Outputs | Customers |
|---|---|---|---|---|
| Vendors | Invoice (paper or PDF) | 1. Receive and log invoice | Logged invoice | Accounts payable team |
| Purchasing | Purchase order | 2. Match to purchase order | Matched invoice | Budget owners |
| Receiving dock | Goods receipt record | 3. Resolve mismatches | Approved invoice | Vendors |
| Budget owners | Approval decision | 4. Approve for payment | Payment | Vendors |
| ERP system | Payment terms | 5. Release payment | Payment confirmation | General ledger team |
Rows are not linked across columns. Each column is its own list, and the row only gives it a place on the page. Boundaries here are "Invoice received" to "Payment released". Vendor onboarding is out of scope, even though missing vendor data may cause some mismatches. That cause goes on a parking list for the sponsor.
Checking a SIPOC with code
A tollgate reviewer asks the same questions of every SIPOC. You can encode the mechanical ones, which is useful if your team keeps SIPOCs in a shared file.
sipoc = {
"suppliers": ["Vendors", "Purchasing", "Receiving dock", "Budget owners"],
"inputs": ["Invoice", "Purchase order", "Goods receipt record"],
"process": [
"Receive and log invoice",
"Match to purchase order",
"Resolve mismatches",
"Approve for payment",
"Release payment",
],
"outputs": ["Logged invoice", "Approved invoice", "Payment confirmation"],
"customers": ["Accounts payable team", "Vendors", "General ledger team"],
"start_trigger": "Invoice received",
"end_point": "Payment released",
}
def check_sipoc(s):
problems = []
for column in ("suppliers", "inputs", "process", "outputs", "customers"):
if not s.get(column):
problems.append(f"{column} is empty")
steps = len(s.get("process", []))
if steps and not 4 <= steps <= 7:
problems.append(f"process has {steps} steps, expected 4 to 7")
for boundary in ("start_trigger", "end_point"):
if not s.get(boundary):
problems.append(f"{boundary} is not defined")
return problems
issues = check_sipoc(sipoc)
print("OK" if not issues else issues)The check cannot tell you whether the SIPOC is right. It only catches gaps. Whether the steps match reality is still a question for the people doing the work.
Common errors
- Too much detail. A twenty-step SIPOC is a flowchart. Combine steps until the page reads at a glance.
- Process described as designed. The documented procedure and the real one differ. Validate with a walk of the process (a "gemba" walk) or with operators.
- Missing customers. Teams list the paying customer and forget the internal receiver of the output, who often defines the real CTQ.
- Boundaries set to avoid hard problems. Cutting the process short at a political boundary can leave the root cause outside the scope. If the cause is likely outside, raise it at the tollgate and let the sponsor decide.
- Treating it as finished. The scope may change after Measure data arrives. Revise the SIPOC and update the charter when it does, with the sponsor's agreement.
SIPOC at the Define tollgate
Reviewers use the SIPOC to check that the charter's scope statement and the map agree. Typical evidence they expect: boundaries that match the charter, customers that match the VOC and CTQ work, and a visible link from the charter's Y to a step or output on the map. A mismatch is a common reason for a conditional go, with the action to reconcile the two documents before Measure begins.
Exercise
A team's SIPOC for a call-centre process has 14 steps and lists only "Callers" as customers. Name two problems and say how you would fix each before the Define tollgate.
Show answer
First, 14 steps is too detailed for SIPOC. Group related steps into four to seven high-level steps and keep the detail for a later process map in Analyze. Second, the customer list is incomplete. Add internal customers who receive outputs, such as the team that handles escalated cases or the billing department that receives call records, and check their requirements against the CTQs. Then confirm the boundaries (the first trigger and the last step) match the scope in the charter.