Improve: designing and testing solutions
This chapter assumes you have worked through Define, Measure and Analyze. You should have a charter with a goal, a baseline such as DPMO (defects per million opportunities) and a short list of root causes verified with data. Here you will see how the Improve phase turns those causes into tested changes, and what evidence the Improve tollgate expects.
Purpose of the Improve phase
Improve exists to change the process so that the verified causes stop producing defects, and to prove that the change works. The phase has three parts:
- Generate candidate solutions for each verified cause.
- Select the solutions that best fit the CTQ (critical to quality) requirement and the project's constraints.
- Test the selected solutions on a small scale and measure the effect against the baseline.
Improve is the first phase in which the process itself changes. Everything before it observes. That is why the tollgate before it, after Analyze, must confirm that causes are verified, not assumed.
Inputs and outputs
The inputs come from earlier phases. The outputs feed Control.
| Item | Source or destination | Purpose |
|---|---|---|
| Verified root causes | From Analyze | Define what each solution must address |
| Baseline DPMO and sigma level | From Measure | Provide the comparison point for pilot results |
| CTQ requirements and goal | From Define | Set the target the solution must reach |
| Selected solutions | Produced here | Record what will change and why |
| Pilot plan and results | Produced here | Show the effect with data |
| Updated process map and risk review | Produced here | Feed the Control plan |
Generating solutions
Work from causes to solutions, one cause at a time. Starting from a favorite fix and looking for a cause to justify it is the most common way an Improve phase goes wrong.
Useful ways to generate options include:
- Brainstorming with the people who do the work. Operators often know which fixes are practical.
- Benchmarking. Look at how another team, site or industry handles the same step.
- Lean ideas. Remove waiting, rework and handoffs. Standardize the step.
- Error-proofing (poka-yoke). Make the mistake impossible or immediately visible. A form that rejects an empty required field is a simple example.
- Reducing variation at the source. Tighten the input, the setting or the method that the verified cause points to.
Prefer solutions that remove the cause over solutions that detect its effect. Added inspection catches defects but does not stop them, and it adds cost and delay.
Checking that every cause is covered
Keep a traceable link from each verified cause to at least one solution. Gaps are easy to miss in a long list. The following script reports causes with no solution and solutions that map to no verified cause.
verified_causes = {
"Unclear label format",
"Manual re-keying of order numbers",
"No check at packing station",
}
solutions = {
"Standard label template": ["Unclear label format"],
"Barcode scan replaces typing": ["Manual re-keying of order numbers"],
"Extra weekly training": [],
}
covered = {c for causes in solutions.values() for c in causes}
uncovered = sorted(verified_causes - covered)
orphans = sorted(name for name, causes in solutions.items() if not causes)
print("Causes without a solution:", uncovered)
print("Solutions without a verified cause:", orphans)Running it shows that "No check at packing station" has no solution and that "Extra weekly training" has no cause. The first is a gap. The second is a candidate to drop or to justify.
Selecting solutions
Selection compares options against agreed criteria, commonly impact on the CTQ, cost, effort, risk and time to implement. A prioritization matrix or an effort and impact grid makes the comparison visible. The next chapter covers selection and pilots in detail, so here the point is the principle: record the criteria before scoring, and let the sponsor and process owner see them. Choices made with hidden criteria are hard to defend at the tollgate.
Piloting and measuring the effect
A pilot is a limited trial of the change in real conditions. It limits the cost of being wrong and produces data. To make the result credible:
- Measure the same Y with the same operational definition and the same measurement system as the baseline. Changing the definition makes before and after incomparable.
- Choose a pilot scope that is representative, not the easiest line or the best team.
- Record anything else that changed during the pilot, such as staffing, volume or season.
- Collect enough data to see the difference. A handful of units cannot separate improvement from chance.
The script below compares the Measure baseline (27 defects in 500 units, 4 opportunities per unit) with a pilot of 200 units that had 5 defects.
from statistics import NormalDist
def dpmo(defects, units, opportunities_per_unit):
return defects / (units * opportunities_per_unit) * 1_000_000
def sigma_level(dpmo_value):
yield_rate = 1 - dpmo_value / 1_000_000
return NormalDist().inv_cdf(yield_rate) + 1.5
baseline = dpmo(27, 500, 4)
pilot = dpmo(5, 200, 4)
print(f"Baseline DPMO: {baseline:.0f}, sigma level: {sigma_level(baseline):.2f}")
print(f"Pilot DPMO: {pilot:.0f}, sigma level: {sigma_level(pilot):.2f}")
print(f"Reduction: {(baseline - pilot) / baseline:.0%}")The baseline is 13,500 DPMO and the pilot is 6,250 DPMO, a reduction of about 54%. The pilot has only 5 defects, though, so the estimate is uncertain. A statistical test, such as a two-proportion test, tells you whether the difference is likely real. Report the test along with the point estimate.
Risk and side effects
Every change can create new problems. Before scaling a solution, review what it might break. A failure mode and effects analysis (FMEA) lists ways the new process could fail, rates each by severity, likelihood and detectability, and assigns actions to the highest risks. Also check effects on other CTQs. A faster inspection step that raises customer complaints has moved the problem, not solved it.
Plan for people as well. Operators who were not consulted may work around the new step. Training, clear instructions and an early look at the pilot by the process owner reduce that risk.
Deliverables for the Improve tollgate
The tollgate reviews evidence, in the same way as the Measure checklist in the earlier chapters. A typical Improve checklist includes:
- Solutions linked to each verified cause
- Selection criteria and the scored comparison
- Pilot plan and pilot results with the same measurement as the baseline
- Statistical evidence of improvement, or a stated reason it is not yet available
- Risk review, such as an FMEA, with actions
- Updated process map and a draft implementation plan
- Confirmation the goal in the charter is met, or a revised goal agreed with the sponsor
Possible outcomes follow the usual set: go, conditional go, hold or stop. A pilot that misses the target but shows a clear path may earn a hold with a defined rework loop. A pilot that shows the goal cannot be reached at acceptable cost may justify a stop.
Common errors in Improve
- Jumping to solutions before causes are verified, then fitting the evidence afterward.
- Skipping the pilot and rolling out at full scale, which makes failures expensive.
- Changing the measurement between baseline and pilot, which makes the comparison meaningless.
- Ignoring side effects on other CTQs, cost or workload.
- Reporting a pilot average without sample size or variation.
Exercise
A team's verified causes are late supplier data, a manual approval step and inconsistent batch labels. Their solution list has an automated data feed, a new approval rule and extra inspection at shipping. Name one gap and one weak solution, and say what to do about each.
Show answer
The gap is the inconsistent batch labels, which have no solution, so the team should generate and select one, for example a standard label template. The weak solution is extra inspection at shipping. It maps to no verified cause and only detects defects after they occur, so the team should drop it or justify it with a link to a verified cause. The team should also confirm that the approval rule addresses the manual approval step.