Sub topic 14
Selecting Solutions and Running a Pilot
This chapter assumes you know the Analyze phase outputs (verified root causes), the baseline measures from Measure (DPMO, sigma level), and the roles of Champion, Black Belt, Green Belt and Process Owner. It covers the middle of the Improve phase: choosing which solutions to try, and testing them on a small scale before full rollout.
Where this step fits
Analyze ends with a short list of verified root causes. Improve turns them into changes. Two activities sit between "we know the cause" and "we are ready for the Improve tollgate":
- Selecting solutions: generating options, then ranking them against agreed criteria.
- Piloting: running the chosen solution on a limited scale and measuring it against the baseline.
The pilot is the evidence the Improve tollgate reviews. Without it, the team can only claim the solution should work.
Generating candidate solutions
Start from the verified root causes, not from favorite fixes. For each root cause, ask what change would remove or reduce it. Useful sources include brainstorming with process operators, benchmarking against a better-performing site, mistake-proofing (poka-yoke), and standard Lean tools such as 5S, standard work and pull systems.
Keep a trace from each solution back to a root cause. A solution that cannot name the cause it addresses is a red flag.
Selecting solutions with a weighted matrix
A solution selection matrix scores each option against criteria and weights the scores. Typical criteria are:
- Impact on the root cause and on the CTQ (the customer requirement from Define).
- Cost and effort to implement.
- Time to implement.
- Risk, including side effects on other processes.
- Acceptance by the people who must use it.
The team agrees on the weights before scoring, so the weights cannot be adjusted to favor a preferred option. Score every criterion so that a higher number is better. For cost and risk, that means a score of 5 for "cheap" or "low risk".
weights = {"impact": 0.40, "cost": 0.20, "speed": 0.15, "risk": 0.15, "acceptance": 0.10}
# Scores 1 (worst) to 5 (best). For cost and risk, 5 means cheap or low risk.
options = {
"Barcode check at packing": {"impact": 5, "cost": 3, "speed": 3, "risk": 4, "acceptance": 4},
"Retrain all packers": {"impact": 3, "cost": 4, "speed": 4, "risk": 5, "acceptance": 3},
"New packing line layout": {"impact": 5, "cost": 1, "speed": 1, "risk": 2, "acceptance": 3},
}
assert abs(sum(weights.values()) - 1.0) < 1e-9
totals = {
name: sum(weights[c] * score for c, score in scores.items())
for name, scores in options.items()
}
for name, total in sorted(totals.items(), key=lambda item: item[1], reverse=True):
print(f"{total:.2f} {name}")The barcode check scores 4.05, the retraining 3.60, and the new layout 3.10. Treat the ranking as a conversation aid, not a verdict. If two options score within a few tenths of each other, the matrix cannot separate them. Discuss the criteria where they differ instead.
Combine options when they address different causes. Piloting a bundle makes it hard to tell which part worked, so keep the bundle small or pilot parts in sequence.
Checking risk before the pilot
Before piloting, run a quick failure mode check (a lightweight FMEA) on the top option. For each way the solution could fail or cause harm, record severity, likelihood and how easily you would detect it. Add mitigations for the high-risk items to the pilot plan.
Designing the pilot
A pilot is a controlled trial, not a soft launch. Write the plan before starting, and include:
- Hypothesis: for example, "The barcode check reduces packing defects from 13,500 DPMO to 7,000 DPMO or lower."
- Scope: one line, shift, site or customer segment, chosen to be representative. Avoid picking the best team because success is likely.
- Success criteria: the metric, the target, and the threshold for "adopt", "adapt" or "abandon", all fixed in advance.
- Duration and sample size: long enough to cover normal variation (shifts, product mix, month-end peaks) and to collect enough units to detect the expected change.
- Measurement: the same operational definitions and the same checked measurement system used for the baseline. A different way of counting defects invalidates the comparison.
- Comparison: the baseline, or better, a concurrent control group running the old process.
- Roles and communication: who runs the pilot, who collects data, who can stop it, and how the affected staff are briefed.
Analyzing pilot results
Compare the pilot with the baseline using the same metric. A better number is not enough, because small samples vary by chance. Test whether the difference is larger than chance would explain.
The baseline from the Measure chapter was 27 defects in 500 units with 4 opportunities each, which is 2,000 opportunities. Suppose the pilot finds 6 defects in 200 units, which is 800 opportunities, or 7,500 DPMO.
from math import sqrt
from statistics import NormalDist
base_defects, base_opps = 27, 2000
pilot_defects, pilot_opps = 6, 800
p_base = base_defects / base_opps
p_pilot = pilot_defects / pilot_opps
p_pool = (base_defects + pilot_defects) / (base_opps + pilot_opps)
se = sqrt(p_pool * (1 - p_pool) * (1 / base_opps + 1 / pilot_opps))
z = (p_base - p_pilot) / se
p_value = 1 - NormalDist().cdf(z) # one-sided: is the pilot better?
print(f"Baseline DPMO: {p_base * 1_000_000:.0f}")
print(f"Pilot DPMO: {p_pilot * 1_000_000:.0f}")
print(f"z = {z:.2f}, one-sided p = {p_value:.3f}")The pilot DPMO is nearly half the baseline, yet z is about 1.33 and p is about 0.09. At the common 0.05 level, this does not show an improvement. The right responses are to extend the pilot, not to declare success, and not to quietly drop the test. This test treats each opportunity as independent, which is an approximation. A Black Belt may prefer a test at the unit level.
Also look at statistical and practical significance together. A real but tiny improvement may not justify the cost of rollout.
Common failure modes
- Pilot effect: people work more carefully when watched. Run long enough for attention to fade, or compare with a control group.
- Unrepresentative scope: a pilot on the easiest line overstates results.
- Moving goalposts: changing the success criteria after seeing data. Record them beforehand.
- Changed measurement: a new inspection method during the pilot mixes the effect of the fix with the effect of measuring differently.
- Side effects ignored: check that the fix did not move the problem elsewhere, such as longer cycle time or more rework downstream.
- No link to cause: the metric improves, but the verified root cause is unchanged, so the gain is probably coincidence.
Evidence for the Improve tollgate
Bring the ranked solution matrix, the risk assessment, the pilot plan, the results against the success criteria (including the statistical test), lessons learned, and a rollout outline. These feed directly into the Control phase, where the control plan locks in the gains.
Exercise
A team pilots a fix on one shift for two days. Defects fall from 2% to 1%, and the Black Belt wants to approve rollout. Give two reasons to be cautious and one action to take.
Show answer
First, two days on one shift is a small sample and may not cover normal variation such as shift or product mix, so the drop may be chance. Second, the pilot effect (extra care while being watched) may explain part of the improvement. Action: extend the pilot, or add a concurrent control group, then test the difference statistically against criteria written in advance.
Exercise
In a weighted selection matrix, why should cost and risk be scored so that 5 means "low cost" and "low risk"?
Show answer
The weighted total only works if a higher score is better on every criterion. If cost were scored the other way, an expensive option would gain points from its cost and the ranking would be distorted.