Sub topic 3
Define: agreeing on the problem and the goal
This chapter assumes you know the five DMAIC phases by name, understand basic process variation, and recognize the roles of Champion, Black Belt, Green Belt and Process Owner. It covers the Define phase: what it is for, what it produces, and where it commonly goes wrong.
Purpose of the Define phase
Define is the first DMAIC phase. Its job is to get the sponsor, the team and the customer to agree on three things before any data work starts:
- Which problem the project will solve.
- Which process it sits in.
- What a successful result looks like.
Skipping this agreement is the most common cause of later rework. A team that begins measuring without it often collects data on the wrong process or chases a goal nobody owns.
Define does not look for causes or propose solutions. Those belong to Analyze and Improve. If the team already "knows" the fix, Define is where that assumption should be written down and then set aside until data can test it.
Main activities and deliverables
| Activity | Question it answers | Deliverable |
|---|---|---|
| Draft the project charter | What are we doing, why, and who is involved? | Signed project charter |
| Gather voice of the customer (VOC) | What does the customer need? | Customer needs and CTQ requirements |
| Map the process with SIPOC | Where does the process start and end? | SIPOC diagram |
| Identify stakeholders | Who is affected or must approve? | Stakeholder list and communication plan |
| Prepare the tollgate | Are we ready to move to Measure? | Evidence package for the Define tollgate review |
The following chapters treat the charter, VOC and SIPOC in more detail. Here the focus is how they fit together.
How the pieces connect
The activities are not independent. VOC defines what the customer cares about. The CTQ (critical to quality) requirement turns that into something measurable. The charter states the problem in terms of the gap against that requirement. SIPOC shows which process produces the gap.
The loop from the tollgate back to the charter is normal. Charters are often revised once or twice before approval.
What makes a good problem statement
A problem statement describes the current gap, not the cause and not the solution. A useful one contains four elements: what is wrong, where it happens, how large it is, and what evidence supports the size.
Compare two versions:
- Weak: "We need a new order-entry system because errors are too high."
- Better: "In the last six months, 8% of customer orders at the Leeds warehouse shipped with a wrong item or quantity, against a customer expectation of under 1%."
The weak version names a solution and gives no number. The better version can be measured, and it does not assume what the fix will be.
The goal statement follows the same discipline. It should be specific, measurable, and tied to a date: "Reduce wrong-item and wrong-quantity shipments at the Leeds warehouse from 8% to under 2% by 31 March." A target taken from the CTQ requirement is easier to defend than one picked by negotiation.
Scope: what is in and out
Scope is the boundary of the work. SIPOC (Suppliers, Inputs, Process, Outputs, Customers) gives a high-level view of that boundary. The charter then records it explicitly as "in scope" and "out of scope".
Scope that is too wide produces a project that never finishes. Scope that is too narrow can miss the real driver. A practical check is whether a Green Belt could complete the work in roughly three to six months. If not, split the problem into several projects.
Also state constraints and assumptions, such as a fixed budget, a system freeze, or an assumption that data is available from the existing warehouse system. Unstated assumptions become surprises in Measure.
Roles in Define
| Role | Contribution in Define |
|---|---|
| Champion or sponsor | Confirms business priority, removes obstacles, signs the charter |
| Black Belt or Green Belt | Leads the project, drafts the charter, runs the VOC and SIPOC work |
| Process Owner | Confirms scope and agrees to take over the process in Control |
| Team members | Provide process knowledge |
| Finance partner | Validates the savings estimate, where one is claimed |
Involve the Process Owner early. A project that the owner did not agree to in Define often fails to hold its gains in Control.
Define tollgate evidence
At the end of Define, the team presents evidence for the decision to proceed. Typical evidence:
- A signed charter with problem, goal, scope, team and timeline.
- Customer needs translated into at least one CTQ requirement.
- A SIPOC diagram agreed by the team.
- A stakeholder list and a plan for communicating with them.
- A realistic estimate of benefit, validated if money is claimed.
The tollgate is a decision, not a presentation. The reviewers decide whether the project is worth the resources it will use.
Common errors
- Solution in the problem statement. Phrases like "implement a new system" lock the team into an answer before analysis.
- No baseline number. If the size of the problem is only a feeling, the goal cannot be tested. A rough number is acceptable in Define, because Measure establishes the proper baseline.
- Goal set without a customer basis. A target of "50% improvement" with no link to a CTQ is arbitrary.
- Oversized scope. "Improve customer satisfaction" is a program, not a project.
- Sponsor in name only. If the Champion does not attend or remove obstacles, the project stalls at the first resource conflict.
- Treating the charter as fixed. The charter can be revised at later tollgates when data shows the original goal was unrealistic, provided the sponsor agrees.
A small checklist for Define
The same pattern used for later tollgates works here. The code below treats the Define tollgate as a checklist of required evidence and reports what is still missing.
DEFINE_TOLLGATE = [
"Problem statement with a number and a source",
"Goal statement with target and date",
"In-scope and out-of-scope boundaries written",
"VOC translated into at least one CTQ requirement",
"SIPOC agreed by the team",
"Sponsor and Process Owner named",
]
def review(checklist, completed):
missing = [item for item in checklist if item not in completed]
if not missing:
return "go", []
return "hold", missing
done = set(DEFINE_TOLLGATE[:4])
decision, gaps = review(DEFINE_TOLLGATE, done)
print(decision)
for gap in gaps:
print("-", gap)Running it prints hold, followed by the two items not yet completed: the SIPOC agreement and the named sponsor and Process Owner.
Exercise
A team writes this problem statement: "Our call center needs a new scripting tool because customers wait too long." List two problems with it and rewrite it so it fits Define.
Show answer
First, it names a solution (a new scripting tool) before any analysis. Second, it has no measurement: "too long" has no number, location or period. A better version: "Between June and November, 35% of calls to the Manchester support center waited more than 3 minutes to be answered, against a customer expectation of under 1 minute." The statement gives the gap, the place, the period and the size, and leaves the cause and the fix open.
Exercise
The sponsor approves the charter, but the Process Owner was never consulted. Explain the risk this creates and which later phase it affects most.
Show answer
The Process Owner will receive the improved process at handover. Without involvement in Define, the owner may disagree with the scope, resist changes in Improve, or not maintain the monitoring in Control. The Control phase is affected most, because sustaining the gains depends on the owner accepting responsibility for them.