Sub topic 15
Control: keeping the gains
This chapter assumes you know the Define, Measure, Analyze and Improve phases, basic control chart ideas (mean, standard deviation, variation), and the roles of Black Belt, Green Belt and Process Owner. The control plan has its own chapter. Here we cover the Control phase as a whole and its tollgate.
Why Control exists
Processes drift back to old habits. A pilot succeeds because the project team watches it closely, and once that attention leaves, people return to the old method, a supplier changes, or a new hire is never trained. Control is the phase that stops this reversion. Its purpose is to make the new level of performance the normal operating state and to move ownership from the project team to the people who run the process.
A project that skips Control often shows good results at closure and then loses them within months. The tollgate at the end of Control has to show that the gain is likely to last, not just that it happened once.
Main activities
Control work falls into five groups.
- Lock in the solution. Prefer changes that are hard to undo. Error-proofing (poka-yoke) changes the process so the mistake can't happen, for example a form that won't submit with a blank field. Automation and system settings come next. Training and reminders are the weakest option because they rely on memory.
- Standardize the work. Update procedures, work instructions and checklists so the improved method is the documented method. Retire the old documents, or the old method will survive in them.
- Monitor with a measure and a rule. Pick the output measure (the Y) and any critical inputs (Xs) to track. Use a control chart so the owner can tell normal variation from a real change.
- Define the response. Write what a person does when a signal appears, who is called, and how quickly.
- Validate benefits and hand over. Confirm the results against the baseline and the charter goal. Have finance confirm any savings. Then transfer the process to the Process Owner.
Monitoring with a control chart
An individuals chart (I-chart) suits measures taken one value at a time, such as daily cycle time. You calculate limits from a stable period after the improvement. The standard estimate of process sigma uses the average moving range (the absolute difference between consecutive points) divided by the constant 1.128. The control limits are the mean plus or minus three of those sigmas.
Two common signal rules are a point beyond a control limit and eight consecutive points on the same side of the center line. The first catches sudden shifts. The second catches small sustained shifts.
from statistics import mean
def individuals_limits(baseline):
moving_ranges = [abs(b - a) for a, b in zip(baseline, baseline[1:])]
center = mean(baseline)
sigma_hat = mean(moving_ranges) / 1.128
return center - 3 * sigma_hat, center, center + 3 * sigma_hat
def signals(values, lcl, center, ucl, run_length=8):
found = []
for i, v in enumerate(values):
if v > ucl or v < lcl:
found.append((i, "beyond limit"))
run_side = 0
run = 0
for i, v in enumerate(values):
side = 1 if v > center else -1 if v < center else 0
if side != 0 and side == run_side:
run += 1
else:
run = 1 if side != 0 else 0
run_side = side
if run == run_length:
found.append((i, f"{run_length} in a row on one side"))
return found
# Cycle time in minutes, collected after the improvement stabilized
baseline = [41.8, 42.5, 41.2, 42.9, 42.1, 41.6, 42.4, 41.9, 42.7, 41.5,
42.2, 42.0, 41.7, 42.6, 41.4, 42.3, 42.8, 41.3, 42.1, 41.9]
lcl, center, ucl = individuals_limits(baseline)
print(f"LCL {lcl:.2f} center {center:.2f} UCL {ucl:.2f}")
# New values collected by the process owner after handover
monitoring = [42.0, 42.4, 41.8, 45.1, 42.2, 42.3, 42.5, 42.6, 42.4, 42.7,
42.3, 42.6, 42.5]
for i, rule in signals(monitoring, lcl, center, ucl):
print(f"point {i}: {rule}")The limits come out near 39.85, 42.05 and 44.24. Point 3 (45.1) is flagged as beyond the upper limit. Point 10 is flagged because points 3 to 10 are all above the center line. Counting starts at 0.
The limits come from the process's own variation, not from the customer's specification. A chart in control can still produce output that misses the CTQ requirement. Check capability separately against the specification.
The response plan and the monitoring loop
A chart with no response plan is decoration. The plan says what the operator does at each signal, and it should separate three cases: a one-off special cause to fix, a sustained shift that needs investigation, and a shift that proves the process has changed and needs a new look at the improvement.
Handover to the Process Owner
Handover is a transfer of accountability, not a file transfer. The Process Owner should be able to run the monitoring without the Black Belt. Before handover, check that:
- The owner has seen the control plan and agrees to it.
- The people who do the work have been trained, and the training is recorded.
- Charts have a named person who updates them and a review rhythm, such as a weekly check.
- A date is set for a follow-up review, often 3 to 6 months after closure, to confirm the gain held.
Lessons learned and replication opportunities also belong here. If the fix works in one line or site, record where else it could apply.
Control tollgate evidence
At the Control tollgate the Champion and the Process Owner look for proof that the change is embedded.
| Evidence | What it shows |
|---|---|
| Before and after data on the Y | The goal in the charter was met |
| Control chart with stable limits | The new level is steady |
| Updated procedures and training records | The method is standard work |
| Response plan and named owner | Someone is accountable after closure |
| Validated benefit sign-off | The financial claim is accepted |
| Signed handover | The project can close |
Typical outcomes are go (close the project), conditional go (close once named gaps are fixed), hold (more evidence needed) or stop. These outcomes are covered fully in the tollgate roles chapter.
Common errors
- Closing on the pilot result. A few good weeks are not proof that the gain is stable. Wait for enough points to set limits and to show stability.
- Relying on training alone. If the only control is "people were told", expect reversion.
- Charting too many measures. Monitor the few that matter. Unread charts are ignored.
- No owner. If the control plan lists a team instead of a person, no one acts on a signal.
Exercise
A team sets control limits from 20 post-improvement points. Later, 8 consecutive points fall above the center line, but none is beyond the upper limit. The operator says the process is in control because no point crossed a limit. Is the operator right, and what should happen next?
Show answer
The operator is not fully right. The run of 8 points on one side of the center line is a signal of a sustained shift even though no limit was crossed. The response plan should be followed: investigate what changed (a supplier, shift, tool or method), fix it if it is a special cause, and record the result. If the new level is real and permanent, review whether the improvement or baseline has changed.
Exercise
Name three items a Champion would expect to see in evidence at the Control tollgate, and say what each one proves.
Show answer
Any three of the following: before and after data on the Y (the charter goal was met); a control chart with stable limits (the new level is steady); updated procedures and training records (the new method is standard work); a response plan with a named owner (someone is accountable after closure); validated benefit sign-off (the savings claim is accepted); a signed handover (the Process Owner accepts the process).