This chapter covers the main deliverable of the Control phase: the control plan. It also covers the handover that moves ownership of the improved process from the project team to the people who run it. It assumes you know the earlier DMAIC phases, the role of the Process Owner, and basic control charts. It also assumes you know what a pilot is and what a baseline is.
Why the control plan exists
Improvements decay. People drift back to old habits, new staff are never trained, equipment wears, and suppliers change. A project that ends with a good pilot result but no way to keep it has only produced a temporary gain.
The control plan is a document that states how the improved process will be monitored, what signals mean trouble, and who responds. It is written for the Process Owner, not for the project team. The project team leaves, and the owner stays.
A control plan answers five questions for each critical measure:
- What is measured, and how?
- How often, and by whom?
- What is the target and the acceptable range?
- What signal means the process is out of control?
- What action follows, and who takes it?
What goes into a control plan
Build the plan around the Y (the output measure from the charter) and the vital few Xs (the verified causes from Analyze). Monitoring the Xs gives early warning, because they change before the Y does.
| Element | What to write | Example |
|---|---|---|
| Characteristic | The Y or X being controlled | Order entry error rate |
| Specification or target | The goal and limits | 13,500 DPMO or lower |
| Measurement method | The operational definition and tool, with the MSA result | Sample audit of 50 orders per day |
| Sample size and frequency | How much, how often | 50 per day, every working day |
| Control method | Chart, checklist, or mistake-proofing | P chart, plus required-field check in the order form |
| Reaction plan | What to do on a signal, and who does it | Supervisor stops release, finds cause, logs it within one shift |
| Owner | A named person, not a team | Order Desk Supervisor |
Two points matter here. First, use the same operational definitions you used in Measure. If the control method counts defects differently from the baseline, you cannot show that the gain held. Second, only control what you have checked. A measure that failed its measurement system analysis (MSA) will produce false alarms or hide real ones.
Choosing control methods
Control methods differ in how much they depend on people remembering things. Prefer the stronger ones.
- Mistake-proofing (poka-yoke) makes the error impossible or immediately obvious, such as a form that rejects a missing field. It needs no vigilance.
- Automation and system settings enforce the new method, for example an alert when a queue passes a limit.
- Statistical process control (SPC) uses control charts to separate normal variation from real change.
- Standard work and checklists document the new method, so it can be trained and audited.
- Audits and management review check that the standard is followed. They are the weakest method, because they rely on people and time.
A good plan usually combines two or three. A written procedure on its own is rarely enough.
Control limits are not specification limits
A common error is mixing up the two. Control limits come from the process data and describe what the process does. Specification limits come from the customer requirement (the CTQ) and describe what the customer will accept. A process can sit inside its control limits and still miss the specification, and the reverse is also possible. The reaction plan should say which one triggers which action.
The following Python sketch computes P chart limits for the daily sample, so the reaction plan has concrete numbers.
import math
def p_chart_limits(p_bar, n):
"""Return (lcl, ucl) for a P chart with a constant sample size n."""
sigma = math.sqrt(p_bar * (1 - p_bar) / n)
lcl = max(0.0, p_bar - 3 * sigma)
ucl = min(1.0, p_bar + 3 * sigma)
return lcl, ucl
# Post-improvement average defect proportion from the pilot, 50 orders a day
p_bar = 0.02
lcl, ucl = p_chart_limits(p_bar, 50)
print(f"LCL: {lcl:.4f} UCL: {ucl:.4f}")
todays_rate = 4 / 50
if todays_rate > ucl:
print("Out of control: start the reaction plan")
else:
print("In control")With these numbers the upper limit is about 0.0794. Four defects in 50 gives 0.08, which is above it, so the reaction plan starts.
Calculate limits from data collected after the improvement, once the process is stable. Limits taken from the old baseline would be too wide, and real problems would not trigger a signal.
The reaction plan
The reaction plan is the part most often left vague. "Investigate" is not a plan. Write down the trigger, the immediate containment, the person responsible, the time limit, and where the result is logged.
Rules that signal trouble can include a point outside the control limits, a run of several points on one side of the centre line, or a steady trend. Pick a small set of rules and state them, because too many rules produce false alarms and people stop reacting.
Handing over to the process owner
Handover is a transfer of responsibility, not a meeting. It is complete when the owner can run, monitor, and defend the process without the project team.
A solid handover includes:
- The control plan, signed by the Process Owner.
- Updated standard work, procedures, and training materials.
- Evidence that the people who run the process have been trained.
- Access to the dashboards, charts, or data sources, with the refresh method documented.
- A documented process map and the verified Xs, so the owner knows what drives results.
- A defined review period, commonly 30, 60, and 90 days, in which the Black Belt or Green Belt is available for questions.
- A financial confirmation, where the project claimed savings, reviewed with Finance.
Where this fits in the Control tollgate
The control plan and handover are the main evidence at the final tollgate. The reviewers check that the plan exists, that the owner has accepted it, that results are sustained, and that lessons and unfinished ideas are recorded. A typical checklist can be modelled like the one used for the Measure tollgate.
CONTROL_TOLLGATE = [
"Control plan signed by the Process Owner",
"Standard work and training updated",
"Monitoring running with reaction plan tested",
"Results sustained over the agreed period",
"Savings confirmed with Finance",
"Lessons learned recorded",
]
def review(checklist, completed):
missing = [item for item in checklist if item not in completed]
return ("go", []) if not missing else ("hold", missing)
print(review(CONTROL_TOLLGATE, set(CONTROL_TOLLGATE[:3])))The flow from signal to response
Common errors
- The plan is written by the project team and handed over without the owner's input, so the owner does not accept it.
- Too many measures are controlled. Limit the plan to the Y and the vital few Xs.
- The reaction plan names a team instead of a person.
- Control limits are calculated from the pre-improvement data.
- Training is treated as a one-time event, and new staff are never covered.
- The plan is never tested. Run a simulated signal and see whether the right person acts.
Exercise
A team's control plan for a call centre lists "average handling time" as its only measure, to be reviewed monthly by "the operations team". The pilot reduced call-back errors, which was the Y in the charter. Name three weaknesses in this plan and how to fix each.
Show answer
First, the measure does not match the charter Y. Control the call-back error rate, and add the verified Xs that drove it. Second, monthly review is too slow to catch a problem early. Sample frequently, for example daily, and use a control chart with stated signal rules. Third, "the operations team" is not an owner. Name one person who is responsible for the reaction plan. A fourth fix is to add a mistake-proofing or system control, so the result does not depend on a monthly review.
Exercise
Using the P chart function above, what are the limits for p_bar = 0.05 and n = 100, and does a day with 12 defects trigger the reaction plan?
Show answer
sigma = sqrt(0.05 x 0.95 / 100) = about 0.0218. UCL = 0.05 + 3 x 0.0218 = about 0.1155, and LCL = max(0, 0.05 - 0.0654) = 0. Twelve defects in 100 is 0.12, which is above 0.1155, so it triggers the reaction plan.