Sub topic 15
Reviewing the Charter and Handling Changes
Assume you know the main sections of a project charter and the roles of sponsor, project manager, and team members. This chapter explains how to keep an approved charter useful when project conditions change.
Why review the charter
A charter is a baseline for the project. A baseline is an agreed reference used to compare current decisions with the original agreement. The charter should not change for every minor adjustment. Review it when a change could affect the project's authorization, boundaries, authority, funding, schedule, or success criteria.
Common review triggers include:
- The business problem or expected benefit has changed.
- A major deliverable is added, removed, or redefined.
- The target date or budget is no longer realistic.
- A key assumption has proved false.
- A major risk has become an active issue.
- The project manager's authority or reporting structure changes.
- A new regulation, dependency, or stakeholder changes the project context.
Routine task decisions usually belong in the project plan or team records. A charter revision is appropriate when the change alters the agreement that makes the project worth doing.
A practical review cycle
Schedule a charter review at project start, at major phase boundaries, and when a trigger occurs. The project manager prepares the proposed change and identifies its effects. The sponsor and other authorized stakeholders then decide whether to approve it.
Use this sequence:
- Describe the proposed change and why it is needed.
- Identify affected objectives, scope items, deliverables, milestones, resources, assumptions, constraints, and risks.
- Compare the expected benefit with the additional cost, delay, or risk.
- Record the decision, approver, date, and effective version.
- Communicate the decision to the team and update related project documents.
Do not silently edit an approved charter. Keep a revision history so people can see what changed and why.
Decide whether a change belongs in the charter
| Change | Charter action |
|---|---|
| Reordering tasks within an approved deliverable | Usually record in the project plan |
| Adding a new deliverable that needs more funding | Revise the charter after approval |
| Replacing a team tool with an equivalent tool | Usually no charter revision |
| Moving the final deadline by two months | Review and likely revise the charter |
A change may require updates in several documents. For example, an approved scope increase might require a revised schedule, budget, risk register, procurement plan, and stakeholder communications. Updating only the charter creates conflicting records.
Common review errors
Teams often treat the charter as a one-time form and never revisit it. They also allow influential stakeholders to change scope through informal conversations. Another error is approving a change without checking whether the project still supports the original business justification.
Before approval, ask:
- Does the project still solve a meaningful business problem?
- Are the objectives still measurable and achievable?
- Does the sponsor still support the investment?
- Are authority, resources, and responsibilities still clear?
- Do the success criteria match the revised scope?
Exercise
The sponsor asks the team to add a reporting dashboard. The dashboard needs extra funding and changes the final milestone. What should the project manager do first?
Show answer
Assess the effect on scope, budget, schedule, risks, and success criteria, then prepare a change proposal for the authorized decision-maker rather than adding the work informally.