Sub topic 6
Naming the Deliverables
This chapter assumes you know the basic roles in a project, including sponsor, project manager, and team member. It also assumes you understand that a charter authorizes a project but does not contain the full project plan.
What a deliverable is
A deliverable is a specific output that the project must produce. It can be a document, product, service, capability, or completed transition. A deliverable should be possible to inspect and accept.
“Work with the new database” is an activity. “Migrated customer database verified against the reconciliation report” is a deliverable.
Name deliverables so that a person outside the day-to-day work can answer these questions:
- What will exist when the project is finished?
- Who is responsible for producing it?
- How will the sponsor know it is complete?
- Which objective or scope item does it support?
Separate activities from deliverables
Activities describe actions. Deliverables describe results. A project charter should emphasize the results because results define what the project promises to provide.
| Activity | Deliverable |
|---|---|
| Configure the new support platform | Configured support platform ready for user acceptance testing |
| Train support staff | Support staff training package and completion record |
| Test the data migration | Data migration test report with unresolved issues listed |
A single deliverable can require many activities. Do not list every task in the charter. Put detailed tasks in the project plan or work breakdown structure.
## 4. Deliverables
| ID | Deliverable | Acceptance evidence | Owner | Target date |
|----|-------------|---------------------|-------|-------------|
| D-01 | Migrated customer database | Reconciliation report shows all required records migrated with approved exception list | Data lead | 2026-05-15 |
| D-02 | Support platform configuration | Product owner signs configuration checklist | Application lead | 2026-05-29 |
| D-03 | Staff training package | Training materials approved and attendance record completed | Training lead | 2026-06-12 |
| D-04 | Operational handover | Operations team accepts support procedures and monitoring instructions | Project manager | 2026-06-26 |Make each deliverable verifiable
Avoid vague nouns such as “improvements,” “support,” or “solution.” Add the form, boundary, or evidence that makes completion observable.
For example:
- Vague: “Better reporting”
- Verifiable: “A weekly service report showing ticket volume, median first-response time, and unresolved tickets”
- Vague: “Data migration”
- Verifiable: “Customer records from the agreed source systems migrated, reconciled, and approved for use”
Acceptance evidence does not need to contain every test detail. It states the proof required for charter-level completion. The project plan can later define test cases, reviewers, and approval dates.
Connect deliverables to scope and objectives
Use identifiers such as D-01 and D-02. Link each deliverable to an objective, scope item, or success criterion. This traceability makes change discussions easier. If someone proposes a new output, you can ask which approved objective or scope item requires it.
A useful sequence is:
List major deliverables only. If an output is small, temporary, or purely internal, record it in the project plan unless excluding it would create confusion about the project's boundary.
Exercise
A draft charter lists “run workshops,” “configure reports,” and “improve decision-making” as deliverables. Rewrite the list so each item describes an inspectable output.
Show answer
Possible revision: “Workshop findings and decision log,” “Configured reports approved by the product owner,” and “Decision-making review report showing the agreed measures and baseline.”