Charter, Business Case, Project Plan and Statement of Work
Assume you already know basic project roles, including the sponsor and project manager, and understand that a project has a defined start and end. This chapter separates four documents that are often confused because they describe the same project from different angles.
The four documents at a glance
A business case explains why an organization should invest in a project. It compares expected benefits, costs, risks and alternatives. It usually supports a decision about whether to fund or prioritize the project.
A project charter formally authorizes the project. It records the purpose, objectives, high-level scope, key stakeholders, major risks, budget range and the project manager's authority. The sponsor usually approves it.
A project plan explains how the approved project will be delivered. It combines detailed plans for schedule, work, resources, communication, risks, quality and changes. The project team uses it to coordinate execution.
A statement of work, or SOW, describes the work that one party will perform for another. It defines required services or deliverables, responsibilities, assumptions, deadlines and acceptance conditions. An SOW is common when an external supplier is involved, but organizations also use it for internal work agreements.
| Document | Main question | Typical owner or approver | Main use |
|---|---|---|---|
| Business case | Why should we do this? | Sponsor or investment group | Decide whether to invest |
| Project charter | What are we authorizing? | Sponsor | Start and govern the project |
| Project plan | How will we deliver it? | Project manager and team | Manage the work |
| Statement of work | What work must one party provide? | Customer and supplier | Define an agreement |
How the documents connect
The documents normally form a sequence, although an organization may create or update them in a different order.
The business case may recommend several options. After a decision to proceed, the charter turns that decision into an authorized project. The project plan then expands the charter into actionable work. If a supplier will perform part of the work, the SOW defines that supplier's commitment and how the customer will accept it.
These documents should agree on important facts. For example, a charter objective to reduce response time to two hours should not lead to a project plan or SOW that excludes the tools needed to measure response time.
Distinguishing boundaries in practice
Consider a project to replace a customer support platform:
- The business case compares platform costs with the expected benefit of faster support.
- The charter authorizes the replacement, names the sponsor and project manager, and excludes a redesign of the public website.
- The project plan schedules configuration, data migration, training, testing and rollout.
- The SOW tells an implementation vendor which configuration, migration and training services it must provide, including acceptance tests.
Small organizations sometimes combine these documents in one file. That is acceptable if each purpose remains clear. A document becomes confusing when it mixes a funding argument with detailed task assignments or treats a supplier's promise as the project's complete plan.
A practical review test
When reviewing a draft, ask:
- Does it explain whether the project is worth doing?
- Does it authorize a defined project and name decision authority?
- Does it explain how the team will execute the work?
- Does it state exactly what a supplier or delivery party must provide?
- Do scope, dates, outcomes and acceptance conditions agree across documents?
Exercise
A sponsor has approved a project charter, but a vendor has not yet been selected. Which document should describe the vendor's future deliverables and acceptance conditions?
Show answer
The statement of work. It can be prepared for procurement and then finalized as part of the agreement with the selected vendor.