Sub topic 14
Getting the Charter Approved
Assume you understand the roles of sponsor, project manager, team member, and stakeholder. At this stage, the charter should already describe the project's purpose, objectives, scope, deliverables, resources, assumptions, constraints, and high-level risks. Approval turns that draft into an authorized project baseline.
What approval means
Approval is a decision by the person or group with authority to start the project. Usually, the project sponsor approves the charter. The sponsor accepts the business justification, commits organizational support, and gives the project manager authority to coordinate the work.
Approval does not mean that every stakeholder agrees with every detail. Stakeholders should review the parts that affect them, but the sponsor makes the authorization decision. If a stakeholder identifies a serious problem, resolve it before approval or record it as an open decision.
The approval record should identify:
- The approved charter version
- The approval date
- The sponsor or approving body
- Any conditions attached to approval
- The project manager and their decision authority
- The location of the signed or otherwise recorded decision
A practical approval flow
Use a short review process rather than sending an unfinished charter to a large group.
First, ask key stakeholders to check feasibility, scope, dependencies, and risks. Then resolve disagreements and update the document. Next, present the revised charter to the sponsor. The sponsor can approve it, reject it, or approve it with conditions.
A condition might require a budget review before a later phase. Record the condition with an owner and due date. Do not treat conditional approval as unrestricted authorization.
| Approval item | Question to confirm |
|---|---|
| Purpose and value | Is the expected benefit worth the investment? |
| Scope and objectives | Are the boundaries and measurable outcomes clear? |
| Authority and resources | Can the project manager obtain the stated support? |
| Risks and constraints | Are important threats visible and owned? |
| Decision record | Is the approved version stored where the team can find it? |
When to revise the charter
A charter is not a detailed project plan, so routine task changes do not require charter approval. Revise it when a change affects the project's authorization or boundaries, such as:
- A major change to objectives or expected benefits
- A material increase or decrease in budget, schedule, or staffing
- A change to in-scope or out-of-scope work
- A new risk that changes the project's viability
- A change in sponsor, project manager, or decision authority
Use version numbers and record why each revision was made. The sponsor or governance body should approve material revisions. Keep the earlier approved version so the team can distinguish the original commitment from later decisions.
Exercise
The sponsor approves the charter with a condition that security testing must be funded before launch. What should the project manager do?
Show answer
Record the condition, assign an owner and due date, track it as a governance decision, and avoid treating the approval as permission to launch without the required funding.