Assume you understand basic project roles, such as sponsor, project manager, and team member. This chapter focuses on the early estimate recorded in a project charter. It is not the detailed cost baseline used to control spending later.
What the charter estimate should contain
The charter should state the expected cost, the resources needed, and the confidence of the estimate. Resources include people, equipment, software, facilities, and outside services.
Separate labor from non-labor costs. This makes the estimate easier to review and update.
| Cost category | Example | Estimating basis |
|---|---|---|
| Labor | 240 analyst hours at $75 per hour | Estimated hours multiplied by rate |
| Software | One-year reporting license | Vendor quote |
| Equipment | Test devices | Recent purchase price |
| Contingency | 10% of estimated costs | Risk and uncertainty |
A useful summary might say: “The project is expected to cost $78,000, with a planning range of $70,000 to $90,000. The estimate assumes two analysts are available for six months and excludes ongoing support after launch.”
Build the estimate
Start with the work
Use the planned deliverables and break them into major work packages. Estimate the effort for each package, then identify who or what is required to complete it.
For labor, record:
- Role or resource type
- Estimated hours or days
- Cost rate
- Availability during the project
- Any specialist skills required
For non-labor costs, record the quantity, unit price, and purchase timing. Include costs that the project must pay even when they are easy to overlook, such as training, travel, data migration, testing environments, or vendor setup fees.
Add contingency deliberately
Contingency is money reserved for identified uncertainty. It is not permission to spend without review. A simple early estimate can apply a percentage to the subtotal, but the percentage should reflect the project's uncertainty.
labor = [
{"role": "Business analyst", "hours": 320, "rate": 75},
{"role": "Developer", "hours": 640, "rate": 95},
{"role": "Tester", "hours": 240, "rate": 65},
]
nonlabor = {
"software licenses": 6000,
"training": 3500,
}
labor_total = sum(item["hours"] * item["rate"] for item in labor)
nonlabor_total = sum(nonlabor.values())
subtotal = labor_total + nonlabor_total
contingency = subtotal * 0.10
total = subtotal + contingency
print(f"Labor: ${labor_total:,.0f}")
print(f"Non-labor: ${nonlabor_total:,.0f}")
print(f"Contingency: ${contingency:,.0f}")
print(f"Planning estimate: ${total:,.0f}")Check resource capacity
A budget can be affordable but still impossible to deliver. Compare the required effort with people's available time. Also check whether a required role is shared with another project. State capacity constraints in the charter so the sponsor can resolve conflicts early.
Common errors
Avoid false precision. An estimate of $82,417 suggests more certainty than an early charter usually supports. Use a rounded figure or a range when the inputs are uncertain.
Do not hide resource assumptions. “Two developers available from January” is more useful than “development resources assigned.” Do not count only project staff. Include vendors, subject-matter experts, reviewers, and operational staff who must support the work.
Finally, state who owns the budget and what spending authority the project manager has. The charter can authorize planning without authorizing every purchase.
Exercise
A project has a labor subtotal of $50,000 and non-labor costs of $10,000. The team applies 15% contingency. What planning estimate should the charter show?
Show answer
The subtotal is $60,000. Contingency is $9,000, so the planning estimate is $69,000. The charter should also record why 15% was chosen and what the estimate excludes.