Listing High-Level Risks
This chapter assumes you understand basic project roles, including the sponsor and project manager, and that you can describe a project’s scope and major deliverables. You will learn how to record risks in a charter without turning the charter into a detailed risk register.
What a high-level risk is
A risk is an uncertain event or condition that could affect a project’s objectives. The effect may be harmful, such as a delay or cost increase. It may also be beneficial, such as an opportunity to finish early.
A charter records only risks that could influence the project’s authorization, boundaries, funding, schedule, or expected benefits. It does not need every technical issue that a team might encounter.
Describe each risk with its cause and possible effect:
- Cause: The vendor has limited migration experience.
- Risk event: The data migration may take longer than planned.
- Effect: The launch milestone may slip and support costs may increase.
This structure is more useful than writing “vendor problems” or “migration risk.”
Selecting risks for the charter
Start by reviewing the project’s assumptions, constraints, objectives, budget, and milestones. Ask:
- What could prevent the project from meeting its objectives?
- Which uncertainty could require a sponsor decision?
- Which event could change the approved scope, budget, or schedule?
- Which dependency is outside the project manager’s control?
- Which assumption, if false, would change the project’s feasibility?
Include risks that are both plausible and consequential. Avoid listing minor issues that the team can handle through normal work planning.
The following table shows an appropriate level of detail:
| Risk | Possible effect | Initial response or owner |
|---|---|---|
| The data owner may not approve field mappings by the design milestone. | Testing and launch could be delayed. | Confirm review dates; sponsor owns escalation. |
| The selected vendor may increase its implementation fees. | The project could exceed its approved budget. | Include a price cap in the contract; procurement monitors it. |
| Support staff may have limited time for training. | Adoption and service quality may suffer after launch. | Reserve training time; support manager owns attendance. |
Assessing and responding to risks
At charter stage, use a simple assessment. Rate each risk by probability, the chance that it will occur, and impact, the size of its effect if it occurs. You can use low, medium, and high rather than pretending to know precise percentages.
A response states what the project will do about the risk:
- Avoid: Change the approach so the risk no longer applies.
- Reduce: Lower its probability or impact.
- Transfer: Give responsibility to another party, often through a contract or insurance.
- Accept: Monitor the risk and prepare a fallback if it occurs.
Assign an owner who can monitor the risk or arrange a response. The owner does not necessarily fix the problem alone.
Connecting risks to governance
High-level risks help the sponsor understand what approval involves. A risk with high impact may require funding, a contingency reserve, a decision deadline, or a change to the project’s objectives.
Review the risks before approval. After approval, move detailed analysis, response tasks, triggers, and status updates into the project’s risk register. Revise the charter only when a risk changes the project’s fundamental assumptions, scope, budget, schedule, or authority.
Exercise
A charter lists “the team might have technical problems.” What should you change?
Show answer
Describe the cause, uncertain event, and effect. For example: “The legacy system may not support the required data export, which could delay migration testing.” Then assess probability and impact, name an owner, and record an initial response.