Defining What Is in Scope and Out of Scope
Assume you understand basic project roles, including the sponsor and project manager. This chapter focuses on scope: the agreed boundary around the work. Scope defines what the project will produce and what it will deliberately leave out.
What scope means
Project scope is the collection of work required to produce the project's agreed results. A scope statement should answer two questions:
- What work and outcomes belong to this project?
- What related work does not belong to this project?
For example, a project to migrate a customer database might include preparing data, configuring the new platform, migrating current records, and training support staff. It might exclude redesigning the customer website and migrating archived records older than seven years.
Explicit exclusions matter because projects attract reasonable requests that still do not fit their purpose, budget, or deadline.
Separate scope from deliverables
A deliverable is a specific product, service, or result that the project produces. Scope describes the boundary of the work needed to create those deliverables.
For a customer database migration:
| Scope element | Example |
|---|---|
| In scope | Clean, map, and migrate active customer records |
| Deliverable | Migrated active customer database |
| Out of scope | Redesign the customer-facing website |
A useful scope section groups inclusions and exclusions by subject. Avoid vague phrases such as “improve the system” or “handle related tasks.” These phrases make disagreements likely because different people assign different meanings to them.
## Scope
**In scope**
- Map customer fields from the old platform to the new platform
- Migrate active customer records created within the last seven years
- Test record counts, required fields, and sample customer histories
- Train 25 support staff on the new search and update workflow
**Out of scope**
- Redesign the public website
- Migrate archived records older than seven years
- Add new customer-support features after launch
- Provide permanent administration after the 30-day transition periodDraw the boundary
Scope decisions should connect to the project's objective, constraints, and deliverables. Ask these questions for each proposed activity:
- Does it directly support an approved objective?
- Is it needed to produce an agreed deliverable?
- Can the current budget, authority, and timeline support it?
- If it is excluded, who owns the work or decision later?
The fourth question prevents an exclusion from becoming an unowned problem. Record the future owner when possible.
Handle scope changes
Once the sponsor approves the charter, a new request should be assessed as a proposed change. Do not silently add it to the project. Record its effect on time, cost, resources, risks, and existing deliverables. The sponsor or designated governance group then decides whether to approve the change.
A clear scope statement gives the project manager evidence for that discussion. It also lets the team reject accidental scope growth without rejecting the underlying business need.
Exercise
A stakeholder asks the migration team to redesign the public website because customers will use the new database through that website. Should the redesign automatically enter scope?
Show answer
No. The team should assess whether the redesign supports an approved objective and whether the charter's budget, schedule, and authority cover it. If not, record it as out of scope and identify its owner or submit it through change control.