Recording Assumptions and Constraints
This chapter assumes you understand basic project roles, including the sponsor and project manager, and that you have seen the project’s objectives and scope. You will record the conditions that shape the project before detailed planning begins.
Assumptions and constraints
An assumption is something the team accepts as true for planning, even though it has not been fully verified. A constraint is a limit that the project must work within. The difference matters because an assumption may change, while a constraint normally requires a trade-off or formal decision.
| Item | Meaning | Example |
|---|---|---|
| Assumption | A planning belief that may need verification | A subject-matter expert will be available for two days each week |
| Constraint | A fixed limit on the project | The project must finish before the current contract expires |
Record assumptions and constraints in the charter because they explain why the project plan looks the way it does. They also give the team an early warning when the plan no longer matches reality.
How to write useful entries
Avoid vague statements such as “Resources will be available.” Name the resource, timing, owner, and effect on the project.
A useful entry answers these questions:
- What is assumed or limited?
- Who owns verification or management of it?
- When must it be checked?
- What happens if it changes?
- Which objective, deliverable, milestone, or risk does it affect?
For example, “The legal team will review the data-retention design by 15 May” is more useful than “Legal approval is expected.” The first statement has a team, an action, and a deadline.
Constraints can involve time, cost, people, technology, regulations, quality, or dependencies on other projects. An approved budget cap is a constraint. A preferred technology is usually an assumption or decision, unless an authority has made it mandatory.
Add assumptions and constraints to the charter
Keep the list short and relevant. The charter is not a detailed issue log. Include conditions that could change the project’s authorization, boundaries, funding, schedule, or expected results.
## 9. Assumptions and Constraints
### Assumptions
| ID | Statement | Owner | Check by | If false |
|----|-----------|-------|----------|----------|
| A-01 | The customer-data owner will provide field definitions by 15 May. | Data lead | 15 May | Replan the migration design |
### Constraints
| ID | Statement | Impact |
|----|-----------|--------|
| C-01 | The migration must be complete before the current platform contract ends on 30 September. | Limits testing and deployment windows |
| C-02 | The approved delivery budget is $120,000. | Requires sponsor approval for extra funding |When an assumption becomes false, do not silently edit the charter. Assess the effect first. The change may become a risk, issue, scope change, or request to revise the charter. A constraint may also be negotiable, but changing it normally requires the authority that imposed it.
Review before approval
Review every entry with the person who can confirm it or manage its effect. Remove assumptions that have already been verified. Add a check date to the remaining assumptions. Confirm that each constraint is real, current, and understood by the sponsor.
Exercise
The project assumes that a vendor will deliver an integration endpoint by 1 August. The vendor now predicts 15 August, after system testing begins. What should the project manager do first?
Show answer
Assess the schedule and quality impact with the team, record the changed condition as a risk or issue, and determine whether the charter’s milestones or constraints require sponsor approval.