Sub topic 7
Defining How Success Will Be Judged
Assume you already understand the project charter, sponsor, project manager, scope, and deliverables. This chapter focuses on success criteria: the evidence used to decide whether the project achieved its intended result.
From objectives to success criteria
A project objective states the result the project should pursue. A success criterion states how people will verify that result. The criterion should be observable, measurable, and tied to a deadline.
A useful criterion identifies:
- Metric: what you will measure
- Baseline: the current value
- Target: the required value
- Deadline: when the target must be reached
- Limit: a condition that must not be exceeded
For example, “Improve customer support” is an objective but not a test. “Reduce median first-response time from 8 hours to 2 hours by 30 June without increasing headcount” gives the team a measurable test.
Success criteria can cover several dimensions:
- Business outcome, such as lower processing time
- Deliverable acceptance, such as all required features passing review
- Quality, such as fewer than 2% failed transactions
- Adoption, such as 80% of support staff completing training
- Constraint compliance, such as staying within the approved budget
Separate outcomes from deliverables
A deliverable is something the project produces. An outcome is the change that production is meant to create. Completing a new reporting dashboard is a deliverable. Managers using it to reduce weekly reporting work is an outcome.
Record both when they differ. A team can deliver a technically complete system without producing the expected business benefit.
| Area | Baseline | Target and deadline | Evidence |
|---|---|---|---|
| First-response time | Median 8 hours | Median 2 hours by 30 June | Monthly support report |
| Training adoption | 0% trained | 80% trained before launch | Learning-system report |
| Data migration quality | Unknown | 99.5% records validated before release | Migration test results |
Define acceptance evidence
For every criterion, name the evidence and its owner. Evidence might be a report, test result, audit record, customer survey, or signed review. The owner is responsible for collecting it, not necessarily for achieving the result.
Avoid criteria that depend only on opinion:
- “Users like the new process”
- “The system is easy to use”
- “The project is high quality”
Replace them with a defined method, sample, threshold, and date. For example, “At least 4 out of 5 in a survey of 30 support agents before launch” can be checked.
from statistics import median
response_hours = [1.5, 2.0, 2.5, 3.0, 1.0]
target_hours = 2.0
observed = median(response_hours)
status = "pass" if observed <= target_hours else "fail"
print(f"Median response time: {observed} hours")
print(f"Criterion: {status}")Handle trade-offs and exceptions
A charter should state what happens when criteria conflict. For example, a faster launch might increase defect rates. Set a priority or a non-negotiable limit:
- The launch date may move by up to two weeks.
- Security and legal requirements cannot be waived.
- The project must remain within the approved budget unless the sponsor approves a change.
Do not add criteria that the project cannot influence or measure. If a benefit depends on later operational work, record the dependency and identify who will measure the benefit after closure.
Exercise
Rewrite “The migration should be reliable” as a measurable success criterion.
Show answer
Example: “At least 99.5% of active customer records pass field-level validation before launch, with all exceptions documented and approved by the data owner.”