Sub topic 5
Workstreams That Run Across the Phases
This chapter assumes you know the six SAP Activate phases by name (Discover, Prepare, Explore, Realize, Deploy, Run) and basic project management terms such as deliverable and milestone. It explains how workstreams cut across those phases.
Phases and workstreams
Phases describe when work happens. A workstream describes what kind of work it is. A workstream is a group of related tasks, owned by one team or role, that continues across several phases. Think of phases as columns and workstreams as rows in a grid. Each cell holds the tasks, deliverables and accelerators for that workstream in that phase.
The roadmap in SAP Activate groups tasks by workstream. The exact list depends on the roadmap you select, so check yours in the roadmap viewer. The workstreams below appear in most S/4HANA roadmaps.
| Workstream | Typical concern |
|---|---|
| Project management | Plan, budget, risks, governance, status reporting |
| Solution adoption | Change management, training, user readiness |
| Application design and configuration | Fit-to-Standard results, configuration, extensions |
| Data management | Data migration scope, mapping, load, validation |
| Testing | Test strategy, test cases, execution, defect handling |
| Technical architecture and infrastructure | Landscape, sizing, interfaces, security |
| Operations and support | Support model, monitoring, handover to run |
How a workstream changes by phase
The same workstream does different things as the project moves forward. Data management shows this well.
- Prepare: define the data migration approach and the objects in scope.
- Explore: confirm which data the business needs in the new system.
- Realize: build and test migration content, then run mock loads.
- Deploy: run the final load during cutover and reconcile the results.
- Run: fix remaining data issues and retire legacy data.
Why dependencies between workstreams matter
Workstreams are not independent. A change in one affects the others, and most schedule problems start at these links.
- Fit-to-Standard decisions in application design set the scope for testing. A new requirement without matching test cases is a gap in quality.
- Data management depends on the application design. Changing a field or process late forces changes to mapping and load programs.
- Solution adoption needs a stable design. Training material written before decisions settle must be rewritten.
- Operations and support must join before Deploy. Otherwise, hypercare starts without people who know the system.
Common errors
- Treating workstreams as separate teams with separate plans. Keep one integrated plan with cross-workstream dependencies visible.
- Starting data and testing work only in Realize. Both need early planning in Prepare and Explore.
- Leaving solution adoption to the end. Change impact is easiest to assess during Explore, when you see which processes change.
- Using every workstream from the template. Tailor the list to your scenario and deployment model, and remove tasks that do not apply.
Exercise
A team finishes Explore and finds that late changes to the Fit-to-Standard results forced the data management team to rework its field mapping. Which two workstreams were involved, and what practice would reduce this problem?
Show answer
The application design and configuration workstream and the data management workstream. Keeping one integrated plan that shows the dependency, and involving data management in the Fit-to-Standard workshops, lets the team assess the data impact of each decision before it is final.