Quality gates and phase exit criteria
This chapter assumes you know the six SAP Activate phases (Discover, Prepare, Explore, Realize, Deploy, Run) and basic project concepts such as deliverables and milestones. It explains how quality gates control the move from one phase to the next.
What a quality gate is
A quality gate is a formal checkpoint at the end of a phase. The project team shows that the phase deliverables are complete and meet agreed criteria. Sponsors and stakeholders then decide whether the project may enter the next phase.
A gate is a decision point, not a status meeting. The possible outcomes are to proceed, to proceed with conditions, or to hold until open issues are closed.
Why gates matter
Problems found late cost more to fix. A scope gap that surfaces during Realize can force rework in configuration and testing. The same gap found at the Explore gate is only a backlog item. Gates make you check scope, quality and readiness at fixed points instead of assuming they are fine.
Gates across the phases
The exact gate names and checklists come from your roadmap, so confirm them in the roadmap viewer. The table below shows typical focus areas.
| Phase | Typical exit question | Example evidence |
|---|---|---|
| Discover | Is there a justified case to proceed? | Business case, chosen scenario, high-level scope |
| Prepare | Is the project ready to start work? | Project plan, governance, team, system access |
| Explore | Is the scope agreed and understood? | Fit-to-Standard results, prioritized backlog |
| Realize | Is the solution built and tested? | Test results, extensions, data migration rehearsals |
| Deploy | Is the business ready to go live? | Cutover plan, user training, go-live decision |
| Run | Is the system stable and handed over? | Hypercare closure, support handover |
Writing good exit criteria
Exit criteria are the conditions a gate checks. Weak criteria cause most gate failures. Good criteria are:
- Measurable. "All critical test cases passed" is checkable. "Testing went well" is not.
- Agreed early. Set them at the start of the phase, not when the gate arrives.
- Tied to deliverables. Each criterion points to a specific document, result or approval.
- Owned. One named person confirms each criterion.
Common errors
- Treating the gate as a formality. If every gate passes without discussion, the criteria are probably too loose.
- Moving the gate date instead of fixing the cause. A late gate with the same open issues only delays the problem.
- Skipping tailoring. Roadmaps are templates. Remove criteria that do not apply to your scenario, and add ones your project needs, such as extra checks for a system conversion.
- Ignoring conditional passes. If you proceed with conditions, record each condition, its owner and its due date.
Exercise
At the Explore gate, the team reports that two Fit-to-Standard workshops were skipped because key business users were unavailable. The sponsor asks whether to pass the gate. What are the sensible options, and what should be recorded?
Show answer
Hold the gate until the workshops are held, or pass with conditions if the skipped areas are low risk. Either way, record the decision, the affected scope areas, the condition that the workshops be completed by a fixed date, and an owner. Passing without a record risks unreviewed gaps surfacing in Realize.